From Static Preset to Dynamic Response: A Dynamic Buffer Management Framework for Sustainable Hydroelectric Project Delivery Based on Risk Correlation and Schedule Prediction

Xiangtian Nie, Gang Luo, Jianuo Gu, Hui Yu, Yi Jian, Bo Wang, Tianyu Fan

Key points

From the paper's conclusion
  • Through a closed-loop mechanism of “risk quantification → buffer calculation → schedule forecasting → dynamic allocation,” the proposed framework transforms schedule management from static presetting to adaptive control, improves project resilience and resource utilization efficiency, and supports sustainable project delivery by improving schedule reliability and reducing unnecessary buffer alloca

Abstract

Large-scale hydroelectric projects play an essential role in sustainable energy infrastructure, yet their construction schedules are frequently disrupted by complex risk correlations and propagation effects. Traditional critical chain buffer management methods often rely on static presets, impeding dynamic allocation. This paper proposes a dynamic monitoring framework for critical chain buffers that enhances schedule resilience by accounting for risk interdependencies. The method employs a fuzzy DEMATEL-ISM-BN algorithm to identify risk propagation paths and quantify their impact on buffers; combines a WBS-RBS mapping matrix with fuzzy expert scoring to determine activity risk weights; uses a PSO-RF model to predict the actual activity completion times; and defines three buffer consumption scenarios based on the predictions to trigger dynamic reallocation. The approach is demonstrated through a case study of a pumped-storage power station in East China. The calculated project buffer was increased from 19.51 days under the root variance approach to 30.56 days after incorporating risk compensation, representing an increase of 56.6% and demonstrating the additional protection required when risk interdependencies are considered in buffer sizing. When critical activities encounter unexpected risks, the dynamic reallocation mechanism promptly redistributes buffers to compensate, preventing delays from propagating downstream along the critical chain. Under the case-study scenario, the total remaining buffer at project completion was 101.09 days. After accounting for the risk-induced extension of activity M, the resulting critical chain duration was 1940.05 days, which was 97.50 days (approximately 4.79%) shorter than the planned critical chain schedule of 2037.55 days. The proposed mechanism enables unused buffer from completed activities to be transferred to subsequent activities, thereby improving buffer utilization efficiency during project execution. Through a closed-loop mechanism of “risk quantification → buffer calculation → schedule forecasting → dynamic allocation,” the proposed framework transforms schedule management from static presetting to adaptive control, improves project resilience and resource utilization efficiency, and supports sustainable project delivery by improving schedule reliability and reducing unnecessary buffer allocation.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers