Engineering Research Express

Schedule Risk Evaluation of Pumped Storage Power Plants Based on WBS-RBS and a Combined Weighting Two-Dimensional Cloud Model

Tianyu Fan, Hongzhe Qin, Zhiqiang Fu, Ruidong Wang, Hao Dong, Zhiyong Li

Key points

From the paper's conclusion
  • Therefore, the scientific evaluation of construction schedule risk is of great importance for improving schedule risk management in pumped storage power plants.

Abstract

As a mature large-scale energy storage technology and a key infrastructure for ensuring the safe and stable operation of power grids, pumped storage power plants have broad development prospects. However, due to multiple uncertainties related to geology, technology, and management, these projects face significant schedule delay risks. Therefore, the scientific evaluation of construction schedule risk is of great importance for improving schedule risk management in pumped storage power plants. To address the limitations of existing studies, including unsystematic risk identification and the limited applicability of current weighting methods and evaluation models, this paper proposes a schedule risk evaluation method for pumped storage power plants based on combined weighting and a two-dimensional cloud model. First, the work breakdown structure and risk breakdown structure method are adopted to identify risks and establish a schedule risk evaluation system consisting of 18 second-level indicators across six dimensions: contractor-related risk, design-related risk, owner-related risk, supervision-related risk, natural risk, and social risk. Second, the AHP-CD-IOWA method is introduced to optimize subjective weighting, while the entropy weight method is employed to determine objective weights, and game theory is further used to achieve the optimal integration of subjective and objective weights. Third, a two-dimensional cloud model is applied to conduct a comprehensive evaluation from the two dimensions of risk occurrence probability and risk consequence, thereby enabling the quantitative assessment and visual representation of risk levels. Finally, the TR pumped storage power plant is selected as a case study for empirical analysis. The results indicate that the overall schedule risk of the pumped-storage power station is at a medium level. Among the six primary risk categories, natural risk is classified as medium–high, construction and social risks as medium, design and supervision risks as medium–low, and owner-related risk as low. The evaluation results show good retrospective consistency with the project’s actual schedule records. Based on the risk assessment results, targeted mitigation recommendations are proposed, which can provide a practical reference for schedule risk identification, management priority setting, and risk control in pumped-storage power station projects.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers