Key points
From the paper's conclusion- The results further demonstrate that routings with minimum trench length do not necessarily minimise total investment cost, since limiting the number of conductor types may exclude larger conductor capacities, thereby changing the feasible routing configurations and the conductor types ultimately selected within the system.
Abstract
Inter-array grid optimisation plays a critical role in the technical and economic performance of wind parks and is typically divided into two primary tasks: routing length minimisation and conductor size selection. This work proposes the consideration of three primary tasks, beginning with graph preparation to account for terrain profiles, soft- and hard-exclusion zones, and export cables. Once a graph with viable connection pathways is established, a routing mixed-integer linear formulation for radial arrays, subject to crossing constraints and a maximum number of turbines per string, is presented. This formulation can be adapted to user requirements to include a minimum number of turbines per string, as well as a methodology to determine the minimum number of substation connections required under irregular turbine distributions arising from terrain constraints. Conductor size selection is addressed through a linear approximation of the power flow, enabling the limitation of the number of conductor types used within the system. Routing and conductor size selection may be combined within an integrated approach or implemented as a sequential algorithm to explore trade-offs between trenching and cabling costs. The proposed approaches are evaluated using current turbine ratings and the cable routings of existing onshore and offshore projects. The integrated formulation generally achieves lower total costs, while the sequential approach offers greater modelling flexibility for constrained routing problems. The results further demonstrate that routings with minimum trench length do not necessarily minimise total investment cost, since limiting the number of conductor types may exclude larger conductor capacities, thereby changing the feasible routing configurations and the conductor types ultimately selected within the system.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Geometry-Guided Optimization for Offshore Wind Farm Collection System Routing via Adaptive Circuit PartitioningEngineering Research Express · 2026
- Wind farm array cable routing with a data-driven/heuristic hybrid optimizerJournal of Physics: Conference Series · 2026
- Integrated Optimization of Layout and Inter-Array Cable Design for Floating Offshore Wind FarmsJournal of Physics: Conference Series · 2026
- Strategic and Grid-Aware Maintenance Planning of Offshore Wind FarmsarXiv · 2026
- AC/DC Intensive Scheduling of Offshore Wind Farm Clusters Under Uncertainty: A Confidence Gap Decision Theory ApproachModelling · 2026
- Multi-Objective Optimization of the Ventilation Opening Location in a Cable Trench Considering Heat Dissipation and Duct LengthSymmetry · 2026