Production Planning in the Steel Industry and Its Downstream Manufacturers: A Review of Models and Solution Approaches
Yuming Zhao, Lijie Su, Yang Yang, Gongshu Wang
Key points
From the paper's conclusion- Production at steel plants could also be planned together with production and purchasing at downstream manufacturers.
Abstract
Steel production planning must balance demand and capacity over time while satisfying restrictions on processing and material use. This review examines models and solution approaches for production planning in the steel industry and in downstream equipment manufacturing. The review compares the production decisions, capacity restrictions, and inventories in models for multi-period planning, batching, and material allocation. Multi-period models balance demand, production, and inventories subject to period capacity limits, while batch capacity, product compatibility, and material dimensions restrict batching and allocation decisions. Downstream production and assembly plans determine the quantities and timing of material requirements. Future research could integrate order batching with multi-period production and inventory planning in steel plants. Production at steel plants could also be planned together with production and purchasing at downstream manufacturers.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Research on Steelmaking Production Scheduling Method Incorporating Benders DecompositionJournal of Physics: Conference Series · 2026
- Energy-aware planning of continuous casting and hot rolling considering steel grade upgradesOR Spectrum · 2026
- Optimal Production Scheduling for Multi-Product Mineral ManufacturingarXiv · 2026
- Centralized and Decentralized Production Planning: A Comparative Study of Scheduling Performance in a Multi-Stage Production SystemApplied Sciences · 2026
- Benchmark datasets for predictive maintenance challenges in steel manufacturingFrontiers in Artificial Intelligence · 2026
- Optimizing Flexibility and Commitments: Partially-Adaptive Multi-Stage Matrix Assembly Layout Design ProblemarXiv · 2026