Construction Control of Temporary Steel Arch Falsework for a Long-Span Box Arch Bridge in a V-Shaped Canyon
Yanling Liu, Lei Luo, Baojie Lu, Xin Li, Bing Zhu
Key points
From the paper's conclusion- This study examines the temporary angle-steel truss falsework used for the Nujiang River reinforced-concrete box arch bridge, which has a 100 m clear span.
Abstract
Construction of a long-span concrete arch in a V-shaped canyon requires coordinated control of the temporary falsework, erection stays and closure geometry. This study examines the temporary angle-steel truss falsework used for the Nujiang River reinforced-concrete box arch bridge, which has a 100 m clear span. A towerless rear-anchorage arrangement, construction-stage finite element analysis and a BIM-assisted geometric-control framework are presented. The preloading calculation uses a maximum design water-bag mass of 2480.6 t and gives a maximum displacement magnitude of 101 mm and a peak model stress magnitude of 218.4 MPa. Separately, preloading survey records at 20 points show downward elevation changes of 23–136 mm after three days and unloading recoveries of 14–71 mm. A nominal anchorage comparison is formulated using the adopted pile geometry and shaft-resistance parameters. Numerical closure-length cases illustrate the influence of geometric compatibility on the formed falsework, while three initial-tension histories illustrate the redistribution of erection-stay forces and final deflection profiles. The proposed control framework relates measurements to construction-stage targets through explicit reference states and local force–geometry sensitivities. The study provides a case-based procedure for organising geometric control and the associated structural checks during segmental falsework erection.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Construction Technology for High-Altitude Piece-by-Piece Assembly of a Large-Span Steel Sky Corridor in a Complex Urban Environment: A Case StudyBuildings · 2026
- A BIM-Based Framework for High-Risk Concrete Formwork Support System Design Considering Multi-Component Load CouplingApplied Sciences · 2026
- A Temporary Stay Cable-Assisted Closure-Before-Rotation Method for Long-Span Cable-Stayed BridgesCivilEng · 2026
- Load-Bearing Behavior and Load-Transfer Mechanism of CFST Combined Arches Under Uneven Load in Large-Section TunnelsApplied Sciences · 2026
- Numerical Analysis of the Performance of a Hybrid Anchorage Foundation for Long-Span Suspension BridgesApplied Sciences · 2026
- ANALISIS RESPONS TAHAP KONSTRUKSI–LAYAN PADA DESAIN BOX GIRDER PRATEGANG JEMBATAN PANDANSIMO DENGAN METODE BALANCED CANTILEVERJurnal Rekayasa Sipil (JRS-Unand) · 2026