System Dynamics Modelling for Performance Evaluation of Prefabricated Interspersed Construction
Hui Du, Yu Diao, Jing Du
Key points
From the paper's conclusion- A numerical sweep of the prefabrication ratio from 0.20 to 0.80 changes total construction cost by −5.9% to +8.9% relative to the case value of 0.50 but moves the composite index by less than 0.5%, which locates the leverage of the ratio in the cost channel rather than in the schedule channel.
Abstract
Prefabrication and interspersed (fast-tracking) scheduling are each known to improve construction productivity, yet their combined behaviour has rarely been modelled as a single dynamic system. In this study, a system dynamics (SD) model was built in Vensim to link the prefabrication ratio with interspersed scheduling across four subsystems: schedule, quality, management, and economic benefit. From 36 candidate factors identified in the literature, practitioner interviews, and site experience, 28 were retained through an exploratory factor analysis of 95 valid questionnaire responses (KMO = 0.701; Bartlett’s test significant) and used to screen and structure the indicators entering the model’s 74 equations. The model was simulated for a 28-storey residential case in Beijing over 12 months, and the stochastic flows were run as an ensemble of 100 simulations with different seeds, which places a 5–95% envelope of at most 0.22 index points on the composite trajectory. A one-at-a-time sensitivity analysis shows that the stage ranking is scale-dependent: decoration leads by a factor of 3.9 on the model’s native index but becomes the weakest of the four stages once the stocks are placed on a common scale, so no stage priority is claimed. A numerical sweep of the prefabrication ratio from 0.20 to 0.80 changes total construction cost by −5.9% to +8.9% relative to the case value of 0.50 but moves the composite index by less than 0.5%, which locates the leverage of the ratio in the cost channel rather than in the schedule channel. Formal predictive validation against measured project records is not reported here and is identified as the principal limitation and next step.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Unveiling the Dynamic Propagation of Schedule Risks in Prefabricated Construction Using the Epidemic ModelBuildings · 2026
- Unpacking Barriers to Prefabricated Construction Adoption for Sustainable Development in the Mekong Delta: A Fuzzy Synthetic Evaluation ApproachIOP Conference Series: Earth and Environmental Science · 2026
- Understanding Complexity in Construction Project Management: A Systematic Review and Integrative Framework Linking Complexity, Project Dynamics, Management Approaches, and PerformanceBuildings · 2026
- A discrete-event scheduling framework for structural system selection under crane and crew constraints: application to discuss a hybrid precast buildingArchitecture, Structures and Construction · 2026
- Digital Innovation Across Functional Subsystems of Prefabricated Construction in China: A Patent AnalysisSystems · 2026
- Evaluation of organizational resilience in the construction phase of prefabricated building project based on a combined weighted cloud modelEngineering Construction & Architectural Management · 2026