Unveiling the Dynamic Propagation of Schedule Risks in Prefabricated Construction Using the Epidemic Model
Yiyi Ye, Qianmai Luo
Key points
From the paper's conclusion- These findings indicate that schedule-risk management should integrate early propagation control, timely intervention for latent disruptions, and recovery and protection after risk infection.
Abstract
Prefabricated construction relies on tightly coupled component production, transportation, and on-site installation. Local disruptions may affect project schedules via exposure, infection, recovery, and renewed susceptibility, yet the underlying dynamic mechanisms remain poorly understood. To address this gap, this study shifts the analytical focus from aggregate project schedule performance to the risk states of individual activities and the transitions between these states. A SEIRS (Susceptible–Exposed–Infected–Recovered–Susceptible)-based schedule-risk propagation model is formulated; its equilibrium points and propagation threshold are derived, and numerical scenarios are adopted to investigate the effects of risk propagation, exposure-to-infection transition, recovery, and loss of protection. Under the specified scenarios, the system converges to a nonzero-risk equilibrium when h < 1, whereas risks gradually dissipate when h ≥ 1. Variations in the propagation rate α and recovery rate γ can shift the system across the critical threshold and alter whether risks persist or dissipate. The exposure-to-infection rate β affects the manifestation of risks but does not change the ultimate risk-free outcome within the investigated parameter range. The protection-loss rate μ primarily modulates the proportions of susceptible and recovered nodes, with relatively limited effects on exposed and infected nodes. These findings indicate that schedule-risk management should integrate early propagation control, timely intervention for latent disruptions, and recovery and protection after risk infection. This study establishes a theoretical framework for understanding schedule-risk state transitions in prefabricated construction and facilitates its extended practical application.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Developing a comprehensive risk profile for modular integrated construction during the assembly and final installation phasesInternational Journal of Construction Management · 2026
- System Dynamics Modelling for Performance Evaluation of Prefabricated Interspersed ConstructionBuildings · 2026
- Towards intelligent risk management in prefabricated buildings: a dynamic ontology-based bayesian network approachAin Shams Engineering Journal · 2026
- A hybrid framework for occupational risk prioritization in construction projects using monte carlo simulation and utility theoryScientific Reports · 2026
- Diagnosing Disruption in Data-Scarce Environments: An Integrated RII-TISM-BBN Framework for Public Housing Construction Management in MyanmarBuildings · 2026
- Inferring latent system risk in interdependent construction systems using digital twinsConstruction Innovation · 2026