Understanding Complexity in Construction Project Management: A Systematic Review and Integrative Framework Linking Complexity, Project Dynamics, Management Approaches, and Performance
Walter Antonio Abujder Ochoa, Angela Gabriela Torrico Arce, Oriana Palma Calabokis, Vladimir Ballesteros-Ballesteros, Alfredo Iarozinski Neto
Key points
From the paper's conclusion- Based on these findings, an integrative framework is proposed linking project complexity, dynamic project behavior, management approaches and organizational capabilities, and project performance through recursive feedback relationships.
Abstract
Construction projects are increasingly characterized by uncertainty, interdependence, organizational fragmentation, technological integration, and evolving interactions that challenge the assumptions of traditional linear project management approaches. This study provides a systematic and integrative understanding of complexity in construction project management by identifying its principal dimensions, dynamic behaviors, management approaches, and implications for project performance. A systematic literature review was conducted and reported in accordance with the PRISMA 2020 guidelines, using Scopus as the primary bibliographic database and a supplementary literature update, resulting in a final evidence base of 136 unique sources. Descriptive and bibliometric analyses were complemented by a qualitative synthesis of the reviewed literature. The findings indicate that construction project complexity can be interpreted through five interconnected dimensions: structural, organizational, technological, contextual, and dynamic complexity. Dynamic project behavior is particularly associated with feedback loops, time delays, non-linear relationships, emergence, and evolving interactions among project components. The review further indicates that complexity does not determine project performance independently; rather, outcomes emerge from the interaction between project complexity, dynamic system behavior, and the managerial capacity to coordinate, interpret, and adapt to changing conditions. Lean-oriented approaches, systems thinking, System Dynamics, socio-technical perspectives, governance mechanisms, BIM, and simulation-based approaches provide complementary mechanisms for addressing different aspects of complexity. Based on these findings, an integrative framework is proposed linking project complexity, dynamic project behavior, management approaches and organizational capabilities, and project performance through recursive feedback relationships. The study concludes that complexity should be treated as an inherent characteristic of construction project systems and managed through systemic, adaptive, and integrative approaches rather than through simplification or deterministic control alone.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Coordination mechanisms in digital building permitting: unravelling the dynamic tension between collaboration and complexityBuilding Research & Information · 2025
- Modelling the structural drivers of critical success factor variability: a conception–method interaction framework for project management researchJournal of Modelling in Management · 2026
- Optimizing construction risk management through BIM integration and strategic planningScientific Reports · 2026
- A Structured Framework for Implementing PMBOK Eighth Edition in Construction Projects Based on Alignment AnalysisBuildings · 2026
- Utilization of Building Information Modeling (BIM) for mitigating construction risksJournal of Engineering and Applied Science · 2026
- Charge cognitive de la gestion des contraintes en projet de construction : Enquête quantitativeSHS Web of Conferences · 2026