Explainable Cost Contingency Allocation Under Tail Risk in Road Projects Using CVaR–Shapley
Víctor Ariza Flores, Claudia Sernaque Montalvo, Gerber Zavala Ascaño, Widmar Balbin Lazo, Samir Augusto Arévalo Vidal
Key points
From the paper's conclusion- For a baseline direct cost of S/312.61 million (USD 81.24 million), the P95 contingency was S/26.88 million (USD 6.99 million), whereas the CVaR95 contingency reached S/30.23 million (USD 7.86 million), highlighting the additional severity captured beyond the percentile threshold.
Abstract
Cost contingency estimation in road projects requires not only quantifying the reserve needed under uncertainty but also identifying the risk sources that justify it, particularly under extreme cost scenarios. This study proposes an explainable framework for estimating and allocating cost contingencies under tail risk by integrating Monte Carlo simulation, Conditional Value at Risk (CVaR), Shapley values, and explainable machine learning. The framework was applied to a Peruvian road project considering 16 risk factors, 50,000 simulation scenarios, and 800 Shapley permutations. For a baseline direct cost of S/312.61 million (USD 81.24 million), the P95 contingency was S/26.88 million (USD 6.99 million), whereas the CVaR95 contingency reached S/30.23 million (USD 7.86 million), highlighting the additional severity captured beyond the percentile threshold. Low productivity, unforeseen interferences, quantity variation, adverse weather events, and freight and transportation jointly accounted for 60.41% of the extreme contingency. Variance contribution, predictive SHAP importance, and CVaR–Shapley attribution showed high ordinal agreement but relevant differences in contribution magnitudes and intermediate rankings. The proposed framework transforms an aggregate tail-risk reserve into risk-specific monetary allocations, providing an auditable basis for prioritizing mitigation measures, strengthening budget justification, and supporting risk-informed planning and financial resilience in road infrastructure projects.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- XAI-enabled probabilistic pipeline for predicting delay and cost overrun risk in constructionEngineering Construction & Architectural Management · 2025
- A Feature-Driven Risk Allocation Modeling Methodology for Transport Infrastructure Public–Private Partnership ProjectsJournal of Construction Engineering and Management · 2026
- Prediction of cost contingency in construction projects by introducing machine learning algorithmsJournal of Civil Engineering and Management · 2025
- Partial Cost Information and Empirical Contingency in Building Retrofit Cost PredictionBuildings · 2026
- Progressive Lower Bound Evaluation for Urban Road Renovation SchedulingarXiv · 2026
- AI-Driven Disruption Monitoring for Resilient Construction Supply Chains: Integrating Named Entity Recognition and Reinforcement LearningApplied Sciences · 2026