Partial Cost Information and Empirical Contingency in Building Retrofit Cost Prediction

Nahyun Kwon, Jongmyeong Kim, Hyosoo Moon, Yonghan Ahn, Sojin Park

Key points

From the paper's conclusion
  • The results support an evaluation framework, not demonstrated early-stage forecasting accuracy or a transferable contingency rate.

Abstract

This study retrospectively evaluated partial cost information and empirical contingency in an archived extract of public-building retrofits. The primary reporting sample comprised 246 records, with all 250 retained for sensitivity analysis. Adding four recorded component costs reduced total-cost mean absolute percentage error (MAPE) from 23.35% to 17.30% for genetic-algorithm-weighted case-based reasoning and from 23.05% to 14.68% for Extra Trees. The primary comparison did not establish a larger improvement for Extra Trees. Predicting the remaining cost and adding the observed subtotal produced 12.72% total-cost MAPE, but remaining-cost-weighted absolute percentage error was 19.28% and remaining-cost MAPE was 29.42%. The paired target-route difference also remained uncertain. Additional nested selection across 14 family-target routes yielded 12.64% total-cost MAPE within the same archive. The historical project-level 90th-percentile (P90) allowance was 35.47%; separate training/calibration/evaluation splits achieved 76–98% coverage with empirical P90 allowances calibrated on disjoint records. For the largest-area holdout, remaining-cost weighted error reached 46.74%, and the 35.47% historical allowance covered only 62% of cases. The selected extract differed from the other records in our 419-record research archive. Field timing and project dates were unavailable. The results support an evaluation framework, not demonstrated early-stage forecasting accuracy or a transferable contingency rate.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers

Partial Cost Information and Empirical Contingency in Building Retrofit Cost Prediction — Science Skim