Progressive Lower Bound Evaluation for Urban Road Renovation Scheduling
Robbert Bosch, Patricia Rogetzer, Wouter van Heeswijk, Martijn Mes
Key points
From the paper's conclusion- We develop a progressive lower bound evaluation method: candidate schedules receive quick, optimistic estimates of their traffic impact from machine learning based surrogate models, and these estimates are refined by exact traffic simulation only for promising candidates, so that full evaluation is reserved almost exclusively for schedules that can advance the Pareto front.
Abstract
Urban infrastructure degrades over time, necessitating periodic renovation to maintain functionality and safety. When renovation is delayed beyond the infrastructure's remaining lifespan, costly emergency interventions become necessary to prevent failure. Decision makers must therefore balance expected emergency intervention costs against traffic congestion impacts. We formalize this trade-off as a road network maintenance scheduling problem with uncertain deadlines, which presents optimization challenges including computationally expensive evaluation and an exponentially growing solution space. We formulate the problem as a bi-level multi-objective optimization problem that explicitly accounts for uncertain infrastructure lifespans through probabilistic failure models. We develop a progressive lower bound evaluation method: candidate schedules receive quick, optimistic estimates of their traffic impact from machine learning based surrogate models, and these estimates are refined by exact traffic simulation only for promising candidates, so that full evaluation is reserved almost exclusively for schedules that can advance the Pareto front. Embedded in a multi-objective genetic algorithm, this evaluation strategy improves solution quality by enabling many more iterations within a fixed computational budget. We demonstrate the method's effectiveness and scalability on substantially larger problem instances than previously addressed in the literature: 76 and 80 projects on the Sioux Falls and Anaheim networks, respectively. Under an identical 24-hour computational budget across 30 random seeds, the method completes up to 87 times as many optimization iterations as standard NSGA-II and achieves statistically significant improvements across multiple performance metrics over both standard NSGA-II and a surrogate-assisted baseline.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Optimization-Based Scheduling for Rapid Repair of Disrupted Airport PavementsApplied Sciences · 2026
- Benchmarking Multi-Objective Optimizers for Climate-Stressed Urban Drainage Network Retrofit Planning: A Simulation-Budget ComparisonWater · 2026
- Approximating Pareto frontiers in stochastic multi-objective optimization via hashing and randomizationConstraints · 2026
- Regret-Based Scenario-Tree Construction for Multistage Stochastic Programs with Deterministic ConstraintsarXiv · 2026
- A machine learning optimisation integration for enhanced railway crossing safetyProceedings of the Institution of Civil Engineers - Transport · 2026
- High-Dimensional Simulation-Based Optimization for Low-Carbon Traffic Signal Control in Large-Scale Urban NetworksSymmetry · 2026