An integrated fuzzy multi-criteria decision making and mixed-integer linear programming optimization framework for project risk assessment and response strategy selection: A case study of a liquefied petroleum gas pipeline construction project.
Mohammad Senisel Bachari, Asgar Khademvatani, Mahdi Iranfar
Department of Energy Economics and Management, Tehran Faculty of Petroleum, Petroleum University of Technology, Tehran, Iran.
Key points
From the paper's conclusion- The findings identify 20 distinct risks and 12 viable risk response strategies.
Abstract
Effective project risk management helps to reduce negative outcomes, especially in construction projects. Because project risk management involves many different parts, an integrated approach is needed to cover all phases. This study proposes an integrated framework for risk planning, identification, assessment, and response strategy selection, addressing major weaknesses in traditional risk management methods. The framework systematically identifies risks, their characteristics, and their impact zones. These elements help to evaluate each risk thoroughly. Risk assessment is performed using fuzzy multi-criteria decision-making, fuzzy SWARA (Step-wise Weight Assessment Ratio Analysis) and fuzzy WSM (Weighted Sum Model). The selection of risk response strategies is then formulated as a mixed integer linear programming (MILP) optimization model. This produces an optimal risk response strategy that reduces threats and takes advantage of opportunities. To provide a proof-of-concept illustration of the proposed integrated framework, we present a case study utilizing empirical data from a real‑world liquefied petroleum gas (LPG) pipeline construction project. The findings identify 20 distinct risks and 12 viable risk response strategies. The optimization component successfully selects six out of twelve response strategies. This achieves a 38.9% reduction in total risk value while meeting the project's constraints.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Optimizing construction risk management through BIM integration and strategic planningScientific Reports · 2026
- Multiobjective optimization model for project time and cost management under multiperiod financial constraintsDiscover Civil Engineering · 2026
- Optimizing large-scale multiproduct pipeline scheduling: a novel hierarchical rolling-horizon frameworkExpert Systems with Applications · 2026
- An Uncertainty‐Aware Digital Twin Framework for Dynamic Cost Prediction and Decision Optimization in Transmission Engineering ProjectsEngineering Reports · 2026
- MODIFIED ADAPTIVE WEIGHT RAO-3 ALGORITHM FOR CONSTRUCTION TIME-COST TRADE-OFF OPTIMIZATION PROBLEMSEskişehir Osmangazi Üniversitesi mühendislik ve mimarlık fakültesi dergisi :/Osmangazi Üniversitesi Mühendislik-Mimarlık Fakültesi dergisi · 2025
- An Intelligent Choquet Fuzzy Integral-Based Framework for Risk Assessment in Seismic Acquisition ProcessesProcesses · 2025