A-377 Scaling Point of Care Testing for a Historic Pediatric Hospital Move

Xu Li, Kim Faustin, Van Leung-Pineda

Key points

From the paper's conclusion
  • Through clear communication and cross-departmental collaboration, the team delivered uninterrupted, high quality POCT services supporting both a complex pediatric hospital transition and the launch of an expanded 446 bed campus.

Abstract

Background On September 29, 2024, Children’s healthcare of Atlanta moved 202 patients from Egleston Hospital to the new 446-bed Arthur M. Blank Hospital in fewer than 12 hours, completing one of the largest single-day pediatric hospital moves in the United States. All clinical services, including the Level 1 Pediatric Trauma Center, were transferred and had to be fully operational on Day 1. To support increased capacity and new expended services, the point of care (POC) team reevaluated and redesigned the testing layouts for i STAT, NOVA, and ABL platform. This ensured uninterrupted testing and regulatory compliance from Day 1. Methods A multidisciplinary POC working group – comprising laboratory, nursing, purchasing, and IT leadership - implemented a structured program:Needs assessment: Current and projected workflows were mapped across all clinical areas to define required cartridge validations, expected user volume, and additional new instrument needed for growth.Device strategy and move day planning: The existing devices. were reviewed for performance and utilization. A deployment plan for the new facility specified which devices would be relocated and where additional analyzers were required. Loaner devices were acquired to ensure sufficient coverage during and after the move. Based on each area’s needs, most departments had devices installed and validated at the new facility before move day, while additional devices travelled with critical patients.Validations:New devices and loaners: All newly purchased i STAT, and ABL analyzers and loaners underwent full validation at the new facility following regulatory requirements. Validations were completed before move day, and devices were released for patient testing.Moved devices: Relocated analyzers underwent move validation. Validations occurred in two phases: devices returned before the move were validated and distributed in advance; devices travelling with patients were validated immediately after arrival.LIS: All devices were checked for connectivity. Result transmission, reference ranges, critical values, and “performed by” statement were verified in a test environment prior to the move.Training: A standardized training and competency program for operators was completed prior to go live for new areas. Results POC services were deployed in 38 departments with 4742 operators trained. The fleet expanded significantly: i STAT devices increased from 112 to 218, NOVA glucometers from 44 to 84 , and ABL analyzers from 3 to 4. To prepare for this move, 30 i STAT and 12 NOVA loaners were secured. 28 of 38 departments, including emergency room, PICU, NICU and CACU, received all requested devices on Day 1 which consisted of 90 of iSTAT and 27 of NOVA. There were no transmission delays or no interruption in POCT availability during the 202-patient move. Conclusion The historic single day move from Egleston to Arthur M. Blank Hospital enabled a strategic redesign and expansion of POCT. Through clear communication and cross-departmental collaboration, the team delivered uninterrupted, high quality POCT services supporting both a complex pediatric hospital transition and the launch of an expanded 446 bed campus.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers