A study on multi-objective dispatch of multi-basin hydropower systems and a two-stage solution method
Chengrui Du, Chao Chen, Jinlong Wang, Lili Wang, Boquan Wang
Key points
From the paper's conclusion- The results indicate that the developed model and solution method can effectively yield stable and reliable dispatch plans.
Abstract
To address the multi-objective conflicts between power generation benefits and the guarantee of minimum system output in the joint dispatch of inter-basin hydropower clusters, as well as the challenges in model solving, a multi-objective optimization dispatch model for inter-basin hydropower clusters was developed. This model comprehensively considers constraints such as water balance, reservoir water level control, and hydraulic connectivity, and incorporates the relative membership fuzzy optimization method to achieve a unified evaluation of multiple objectives. Based on this, a two-stage solution framework was proposed, consisting of “initial solution via iterative approximation of the DDDP-optimization via local search correction.” Taking 27 power stations across the Jinsha River (partial section), Yalong River, Wujiang River, and the Three Gorges-Gezhouba cascade as the study subjects, a case study was conducted using long-term runoff data from 1959 to 2012. The results indicate that the developed model and solution method can effectively yield stable and reliable dispatch plans. A significant trade-off exists between the power generation objective and the minimum output objective: when the weight of power generation is too high, minimum output decreases significantly. Conversely, when the weights are close, both power generation benefits and output stability can be balanced. The comprehensive optimal solutions are primarily concentrated in the weight equilibrium range. These findings provide a reference for the coordinated dispatch of hydropower clusters across river basins and for enhancing the power grid’s supply security.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Research on Multi-Time-Scale Optimal Scheduling of Hydro–Solar Complementation in the Shuoqu River BasinEnergies · 2026
- A Retrospective Diagnostic Framework for Multi-Objective Rule Curve Optimization of a Two-Tier Hydropower Reservoir System in Lao PDRWater · 2026
- Day-Ahead Economic Dispatch Optimization for Cascade Hydro–Photovoltaic Complementary Power Generation Systems Based on Dual-Layer Decoupling (DP-MAPPO)Processes · 2026
- Flexible Day-Ahead Scheduling of a Cascade Hydro-Wind-Solar-Thermal-Storage System Including Hybrid Pumped StorageProcesses · 2026
- Optimal Development of Hydropower Storage Potential for Enhancing Flexibility of Cascade Hydro–Wind–Solar SystemsEnergies · 2026
- Flood Season Staging-Based Joint Refill Optimization for Cascade Reservoirs: A Case Study of the Dadu River in Southwest ChinaWater · 2026