Simulating elevator capacity and peak worker flow in high-rise construction projects
Müge Tetik
Key points
From the paper's conclusion- The results show a drastic reduction in waiting times as elevators are added: for the base case, one elevator leads to high accumulated delays, two elevators cut average waiting significantly and three decreases to a substantially under the tested peak load configuration.
Abstract
Construction site capacity planning is usually done through informal processes. Site personnel may end up spending large amounts of time waiting for elevators especially during rush hours. This study develops a simple discrete-event simulation of elevator use. The model uses four work zones across forty floors, varying arrival times and individual workers queuing with limited elevator service capacity. Scenarios with one, two and three elevators were run over multiple replications to get stable average results. The results show a drastic reduction in waiting times as elevators are added: for the base case, one elevator leads to high accumulated delays, two elevators cut average waiting significantly and three decreases to a substantially under the tested peak load configuration. Specifically, adding a second elevator reduced mean waiting time by 35%, third by 58% compared to two-elevator system. The method provides a lightweight way to improve vertical logistics planning decisions early in projects and can be extended with more detailed behavioral assumptions or calibrated to real data.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Using simulation modelling to support decision-making in warehouse internal logisticsProduction Engineering Archives · 2026
- Passive crowd buffering in pre-operational transit stations: a hybrid simulation study of the Thammasat University SRT red line stationRailway Sciences · 2026
- CoSPACE: Coordinated Construction Scheduling, Material Logistics, Shared Storage, and Crew Deployment for Resource-Efficient Site PlanningSustainability · 2026
- Evacuation Performance of Passenger Spaces and Facilities in Underground Subway Stations for Heterogeneous Ambulatory PassengersFire · 2026
- Fixed Hall-Call Assignments and Floor-Ordered Pair Costs in Elevator DispatchMathematics · 2026
- Time-Expanded Network-Based Dynamic Scheduling System for Airport Ferry VehiclesSystems · 2026