Risk prioritization in construction projects as a governance problem: a hierarchical, explainable, and uncertainty-aware decision framework
Sachin Admane, Tejas Admane
Canadian Institutes of Health Research · Japan Society for the Promotion of Science London
Key points
From the paper's conclusion- This study develops and demonstrates a governance-oriented framework for construction project risk prioritisation under uncertainty, reframing risk prioritisation as a decision-structuring problem rather than a purely predictive task.
Abstract
Construction projects increasingly face interacting risk drivers arising from performance pressure, safety-conditions, environmental exposure, and operational stress. Despite advances in digital monitoring and analytics, project risk prioritisation in practice remains dominated by cost and schedule indicators, often leading to delayed or misdirected interventions. This study develops and demonstrates a governance-oriented framework for construction project risk prioritisation under uncertainty, reframing risk prioritisation as a decision-structuring problem rather than a purely predictive task. A hierarchical, explainable, and uncertainty-aware risk governance framework is proposed. Latent risk signals are extracted from performance, safety, environmental, and operational indicators using unsupervised learning techniques, followed by domain-specific risk modelling. Domain-level risk beliefs are integrated through evidential reasoning to derive transparent project-level risk priorities. The framework is empirically evaluated using the BIM–AI Integrated Construction Project Dataset comprising 1,000 construction projects with indicators related to cost performance, scheduling, structural health monitoring, environmental conditions, and operational resource utilisation. Results reveal that safety-related risk beliefs frequently dominate overall project vulnerability and may precede observable cost-schedule deviations. These findings suggest that governance dashboards should incorporate leading safety and operational stress indicators alongside traditional performance metrics to support earlier intervention. Future research should examine longitudinal applications across diverse project contexts.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- XAI-enabled probabilistic pipeline for predicting delay and cost overrun risk in constructionEngineering Construction & Architectural Management · 2025
- Optimizing construction risk management through BIM integration and strategic planningScientific Reports · 2026
- Inferring latent system risk in interdependent construction systems using digital twinsConstruction Innovation · 2026
- Interpreting risk drift in construction projects: a fuzzy–Bayesian decision framework for weak signal–based governanceInternational Journal of Construction Management · 2026
- Development of a hierarchical fuzzy assessment model for quantifying GenAI risks in sustainable construction projectsFrontiers in Built Environment · 2026
- AI-Driven Optimization of Scheduling, Risk, and Sustainability in BIM-Enabled Construction Project ManagementArabian Journal for Science and Engineering · 2026