Implementation of conveyor belt logistics over multiple construction sites for the Brenner Base Tunnel

Oliver de Jager‐Janisch, Christian Schwarz, Sebastian Reimann, Karl Deininger, Stefan Leitner, Dietmar Schaller

Key points

From the paper's conclusion
  • The size of the Brenner Base Tunnel, and the fact that multiple excavation drifts are under way at the same time, require a highly efficient logistics plan covering multiple construction sites to manage the high volume of spoil extracted.

Abstract

The size of the Brenner Base Tunnel, and the fact that multiple excavation drifts are under way at the same time, require a highly efficient logistics plan covering multiple construction sites to manage the high volume of spoil extracted. For several years, two TBM excavations and several sets of excavation works using drilling and blasting were carried out at the same time in the main tunnel stretches under construction in lots H41 (Sill Gorge–Pfons) and H52/H53 (Hochstegen and Pfons–Brenner). The resulting spoil flows far outstripped the capacity of the local disposal sites. In order to ensure that construction time was adhered to and to reduce environmental impacts to a minimum, a conveyor belt system was planned to cover multiple construction sites. Thanks to the breakthrough in the exploratory tunnel and the use of a dedicated landfill site in the Padaster valley, it was possible to coordinates and combine the flow of spoil between the sites. This paper describes the organisational, technical and timing challenges of the conveyor belt interface, the coordination between construction sites and the management of parallel flows of material. The work further describes the results obtained in maintaining construction timing and cutting down both on transport volumes and environmental impacts. This experience shows that integrated planning and cooperation across construction sites can effectively manage complexities in large underground construction projects and sustainably reduce logistics risks.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers

Implementation of conveyor belt logistics over multiple construction sites for the Brenner Base Tunnel — Science Skim