Risk management and TBM performance analysis in deep mechanized tunnelling: Lessons learned from the Austrian section of the Brenner Base Tunnel

Walter Fahrnberger, David Marini, Romed Insam, Wolfgang Holzer, Kurt Mair am Tinkhof, Markus Scheuringer

Review

Key points

From the paper's conclusion
  • This paper presents an evaluation of TBM performance data from construction lot H41 “Sillschlucht–Pfons” and construction lot H53 “Pfons–Brenner”.

Abstract

Risk management in the planning of deep tunnel structures represents a key challenge, particularly in mechanised tunnelling. This is due to geological uncertainties and the limited availability of reliable investigation data during early project phases. The prior construction of an exploratory tunnel, subsequently used as a service tunnel, has proved to be an effective strategy at the Brenner Base Tunnel for significantly reducing existing uncertainties, although residual risks cannot be fully eliminated. This paper presents an evaluation of TBM performance data from construction lot H41 “Sillschlucht–Pfons” and construction lot H53 “Pfons–Brenner”. The analysis focuses on key performance indicators for mechanised tunnelling, in particular advance rates and machine behaviour under varying geological conditions.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers

Risk management and TBM performance analysis in deep mechanized tunnelling: Lessons learned from the Austrian section of the Brenner Base Tunnel — Science Skim