Single-Machine Scheduling with Interval Predictions and Costly Preemption
Lachlan Bridges
Key points
From the paper's conclusion- We study the single-machine total-completion-time problem $1||\sum C_j$ when processing times are unknown but each job comes with a reported interval.
Abstract
We study the single-machine total-completion-time problem $1||\sum C_j$ when processing times are unknown but each job comes with a reported interval. Jobs are initially processed in nondecreasing order of reported upper bound. If a job is still unfinished after receiving that much service, the reported upper bound has been violated and the policy switches to a resumable geometric fallback. Each interruption of an unfinished job incurs an additive penalty $κ$. For a residual set of $m$ jobs, known size ratio $D=s_1/s_0$, normalized interruption penalty $λ=κ/s_0$, and geometric depth $K$, we derive an explicit worst-case coefficient $Ψ_{m,D,λ}(K)$. When $λ>0$, a finite minimizing depth exists and can be chosen after the trigger from the observed number of unfinished jobs; the optimal depth decreases with the interruption penalty and increases with the residual set size. We also derive the exact worst-case coefficient $R_{n,D}$ for an arbitrary nonpreemptive list when all processing times lie in a known bounded range. These bounds give guarantees for valid intervals, a single interval failure, arbitrary reports, no-trigger outcomes, and random instances. In the single-failure regime, they also give a precise condition under which the proved fallback guarantee is smaller than the bounded-range continuation guarantee.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Prediction-Driven Non-Preemptive Scheduling with Bounded Overtaking: A Per-Job Wait GuaranteeMathematics · 2026
- Near-Optimal Consistency-Robustness Bounds for Non-Clairvoyant SchedulingarXiv · 2026
- A QPTAS for Stochastic Scheduling of Bernoulli JobsarXiv · 2026
- Cross-Shift Analysis for Unrelated-Machine Weighted Completion Time A (1.3168+epsilon)-ApproximationarXiv · 2026
- Pareto-optimal Scheduling with PredictionsarXiv · 2026
- Weighted Flow Time Does Not Admit Constant-Competitive Randomized AlgorithmsarXiv · 2026