Integrating CPM, PERT and Earned Value Management for Economic Sustainability in Residential Construction: A Case Study
Patrycja Karcińska, Justyna Jaskowska-Lemańska, Jarosław Malara, Szymon Karlik
Key points
From the paper's conclusion- The findings support the calibration of duration estimates against comparable records and the use of time-based indicators alongside cost measures.
Abstract
Reliable schedule and cost control support the economic sustainability of construction project delivery. This study examines the combined application of the Critical Path Method (CPM), PERT, Monte Carlo simulation, and Earned Value Management (EVM) with Earned Schedule (ES) to residential shell construction in Kraków. A retrospective comparison of the baseline schedule with activity durations and monthly progress records identifies weaknesses in the duration estimates and examines their implications for project control. Construction exceeded the baseline duration by 11.8%. The simulation based on retrospectively elicited duration estimates understated the observed delay, while a sensitivity scenario demonstrated the dependence of completion probabilities on the assumed duration distributions. Earned Schedule retained information about delay at completion, when the conventional schedule performance index returned to unity. Forecast errors varied across construction phases, including a temporary recovery followed by renewed delay. Reported costs for the EVM scope are distinguished from a separate scenario calculation of time-dependent site overheads. The findings support the calibration of duration estimates against comparable records and the use of time-based indicators alongside cost measures. Environmental effects are discussed as potential consequences; they are not quantified by the monetary overhead calculation.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Comparative Analysis of Project Completion Forecasting Using Earned Value Management, Earned Schedule, and Program Evaluation and Review TechniqueJURNAL TEKNIK SIPIL CENDEKIA (JTSC) · 2026
- Analysis Of The Application Of Time Management In Building Projects With Critical Path Method (Cpm) And Earned Value Method (Evm) (Case Study: Jakarta Islamic Hospital Pondok Kopi)JURNAL TEKNIK SIPIL CENDEKIA (JTSC) · 2026
- Expert-Based Schedule-Risk Modeling in Parcel-Scale Urban Regeneration: An Assumption-Sensitivity Analysis in the Context of TürkiyeBuildings · 2026
- Multiobjective optimization model for project time and cost management under multiperiod financial constraintsDiscover Civil Engineering · 2026
- A Structured Framework for Implementing PMBOK Eighth Edition in Construction Projects Based on Alignment AnalysisBuildings · 2026
- AI-Driven Optimization of Scheduling, Risk, and Sustainability in BIM-Enabled Construction Project ManagementArabian Journal for Science and Engineering · 2026