Minimizing Cost Overrun in Rail Projects Through 5D-Bim: The Case Study of Victoria
Osama A. I. Hussain, Robert Moehler, Stuart D.C. Walsh, Dominic D. Ahiaga-Dagbui
Australian Regenerative Medicine Institute · The University of Melbourne
Abstract
This study evaluates the adoption and efficacy of the 5th Dimension Building Information Modelling (5D-BIM) as a cost dimension for mega rail projects, extending the discussion beyond just technological implementation to consider broader policy and practical implications. The purpose of this article is to understand the governance context of 5D-BIM implementation for rail and transport projects and evaluate the effectiveness of the 5D-BIM framework as currently applied by conducting semi-structured interviews with key stakeholders. Drawing on semi-structured interviews with 22 stakeholders across government, industry, and technology providers, the research examines current 5D-BIM practices. While the primary focus of the research is 5D BIM implementations within the state of Victoria, Australia, which is currently experiencing a surge in rail projects, interviews were also conducted with additional stakeholders from international rail projects for context. The findings reveal fragmented adoption, varying levels of organisational maturity, and significant policy and implementation gaps, particularly in the role of government as the primary client of transport infrastructure. The results of the interviews emphasise the centrality of government and regulatory context in driving the adoption and implementation of 5D-BIM as the primary client of transportation infrastructure and identify actionable recommendations for policymakers and practitioners towards a more integrated approach to 5D-BIM in mega rail projects. While 5D-BIM demonstrates clear benefits in enhancing cost estimation, coordination, and decision-making, its effectiveness is constrained by the absence of clear standards, limited BIM literacy, and inconsistent regulatory guidance. This study provides one of the first empirical validations of the 5D-BIM governance framework, demonstrating that its success is driven less by technological capability and more by policy alignment, standardisation, and institutional leadership.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Lean construction and BIM in construction projects: A literature review (2015–2025)Organization, Technology and Management in Construction: an International Journal · 2026
- Framework for extracting project quantities for construction cost estimation using 5D BIM in an openBIM environmentJournal of Engineering Design and Technology · 2026
- IMPLEMENTASI PENGGAMBARAN, PENJADWALAN, DAN ESTIMASI BIAYA DENGAN METODE BIMCRANE Civil Engineering Research Journal · 2026
- Adoption of Building Information Modeling (BIM) to Improve Urban Construction in BangladeshAmerican Journal of Civil Engineering and Constructions · 2026
- An Integrated ML-Lean-BIM framework for prediction of construction duration in metro projectIOP Conference Series: Earth and Environmental Science · 2026
- Toward Smart Railway Infrastructure Predictive and Optimised Maintenance Through Digital Twin (DT) SystemSensors · 2026