An Integrated ML-Lean-BIM framework for prediction of construction duration in metro project
Yuvashree, Greegar George
Key points
From the paper's conclusion- The predicted durations were integrated into Lean-based Takt planning, reducing the construction duration for four piers from 140 days to 42 days, achieving a 70% schedule reduction.
Abstract
Construction projects frequently face schedule delays and cost overruns due to uncertainties in labour productivity, resource availability, and site conditions. This study proposes a novel integrated Machine Learning (ML)-Lean–BIM framework that combines ML-based duration prediction, Lean Takt planning, and BIM-enabled simulation and cost estimation within a unified decision-support workflow for construction planning. Metro rail pier shaft construction was selected as the case study due to its repetitive workflow. Historical construction datasets were analysed using Decision Tree, Random Forest, and Gradient Boosting models developed in the Orange Data Mining platform. Among the evaluated models, Gradient Boosting achieved the best predictive performance with a cross-validation R 2 of 0.866 and a test-set R 2 of 0.999. The predicted durations were integrated into Lean-based Takt planning, reducing the construction duration for four piers from 140 days to 42 days, achieving a 70% schedule reduction. BIM-enabled quantity extraction and cost estimation further demonstrated a 57.61% reduction in construction cost compared with conventional planning methods.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Mapping the state-of-the-art: bibliometric and systematic analysis of machine learning and AI-based cost and time prediction in constructionJournal of Asian Architecture and Building Engineering · 2026
- AI-Driven Automation of Construction Cost Estimation: Integrating BIM with Large Language ModelsBuildings · 2026
- An uncertainty-aware 4D/5D digital-twin framework for cost estimation and probabilistic schedule control: field and benchmark validation from a Texas mid-rise projectDiscover Civil Engineering · 2026
- Advancing Residential Construction Project Planning: From Traditional Time–Cost Models to Machine LearningIOP Conference Series: Earth and Environmental Science · 2026
- AI-Driven Optimization of Scheduling, Risk, and Sustainability in BIM-Enabled Construction Project ManagementArabian Journal for Science and Engineering · 2026
- Unraveling the impact of machine learning on the AEC sector: academia and industry perspectivesArchitectural Engineering and Design Management · 2026