An Integrated ML-Lean-BIM framework for prediction of construction duration in metro project

Yuvashree, Greegar George

Key points

From the paper's conclusion
  • The predicted durations were integrated into Lean-based Takt planning, reducing the construction duration for four piers from 140 days to 42 days, achieving a 70% schedule reduction.

Abstract

Construction projects frequently face schedule delays and cost overruns due to uncertainties in labour productivity, resource availability, and site conditions. This study proposes a novel integrated Machine Learning (ML)-Lean–BIM framework that combines ML-based duration prediction, Lean Takt planning, and BIM-enabled simulation and cost estimation within a unified decision-support workflow for construction planning. Metro rail pier shaft construction was selected as the case study due to its repetitive workflow. Historical construction datasets were analysed using Decision Tree, Random Forest, and Gradient Boosting models developed in the Orange Data Mining platform. Among the evaluated models, Gradient Boosting achieved the best predictive performance with a cross-validation R 2 of 0.866 and a test-set R 2 of 0.999. The predicted durations were integrated into Lean-based Takt planning, reducing the construction duration for four piers from 140 days to 42 days, achieving a 70% schedule reduction. BIM-enabled quantity extraction and cost estimation further demonstrated a 57.61% reduction in construction cost compared with conventional planning methods.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers