Transformer Inrush Mitigation and Sequential Load Restoration in a Hybrid PV–BESS Microgrid Using Grid-Forming Black-Start Control—Case Study of a 31.59 MWp Photovoltaic Plant
Teodora Lazar, Daria Ionescu, Adina Milena Tatar, Dan Cristian Lazar, Otilia Nedelcu, Dragos Pasculescu
Key points
From the paper's conclusion- Overall, the study confirms that the proposed architecture and staged control logic provide a feasible and transferable framework for enhancing the resilience of large-scale photovoltaic power plants based on hybrid PV–BESS microgrids.
Abstract
Hybrid PV–BESS microgrids represent a promising solution for enhancing energy resilience; however, the implementation of black-start functions in such architectures remains a complex challenge, particularly in the presence of medium-voltage transformers and grid-following photovoltaic sources. This paper proposes and evaluates, through MATLAB/Simulink simulation, a black-start strategy for a hybrid microgrid derived from the architecture of a real 31.59 MWp photovoltaic power plant connected through a 20 kV collector network. The strategy is based on a BESS operated in grid-forming mode, responsible for voltage and frequency formation, controlled energization of the internal infrastructure, and support of the initial restoration stages, while the photovoltaic groups are synchronized at a later stage in order to reduce the energy burden imposed on the storage system. The methodology combines controlled voltage ramping for transformer inrush current mitigation, hybrid PV–BESS restoration, robustness evaluation under irradiance variation, sequential load restoration, and staged energization of the internal stations TS1–TS5. The results show that the soft-start strategy reduces the maximum instantaneous current of transformer TS2 from 188.3620 A to 0.3515 A and the maximum current of the BESS source from 4729.2 A to 57.7929 A. In the hybrid scenario, after photovoltaic source synchronization at 7 s, PV power rises to 2.75 MW, while the power supplied by the BESS decreases from 3.00 MW to 0.25 MW. The analysis of irradiance variation confirms the increased energy dependence on the BESS under reduced solar resource conditions, while sequential load restoration demonstrates the feasibility of controlled reconnection up to 30.25 MW. Overall, the study confirms that the proposed architecture and staged control logic provide a feasible and transferable framework for enhancing the resilience of large-scale photovoltaic power plants based on hybrid PV–BESS microgrids.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Coordinated Black-Start Control of a Diesel Generator–V2G System for Enhanced Frequency SupportElectronics · 2026
- Intelligent Modeling of PV–BESS Microgrids for Enhanced Stability, Cyber–Physical Resilience and Blackout PreventionEnergies · 2025
- Energy-Aware Finite-Horizon MPC Coordination of Adaptive VSG Inertia and BESS Control for Transient-Stability Enhancement in Renewable-Dominated Low-Inertia Hybrid Microgrids.Sensors (Basel, Switzerland) · 2026
- Distributionally Robust Whole-Process Restoration of Power Systems with Photovoltaic–Battery Energy Storage Stations and Flexible LoadsApplied Sciences · 2026
- Enhancing microgrid resilience through integrated grid-forming and grid-following inverter strategies for solar PV battery control and fault ride-throughScientific Reports · 2025
- Grey Wolf Optimization-Based Energy Management of BESS for Seamless Grid-Following Operation in PV-Integrated MicrogridsAutomation · 2026