Assessing the impact of AI-enabled BIM digital twins on construction risks: a Bayesian Network of Jordanian expert beliefs.
Faten Albtoush, Ja'far A Aldiabat Al-Btoosh, Taiseer Mustafa Rawashdeh, Mohammed A K A Al-Btoush
Faculty of Engineering, Civil Department, Jadara University, Irbid, Jordan. · Faculty of Engineering Technology, Zarqa University, Zarqa, Jordan.
Key points
From the paper's conclusion- Experts believe that, under idealized, high-readiness conditions, AI-enabled BIM Digital Twins could sharply reduce the probabilities of schedule delays >20% and cost overruns >10%.
Abstract
Building projects in Jordan routinely experience substantial schedule delays and cost overruns, yet robust empirical evidence on the impacts of Artificial Intelligence (AI) and Building Information Modelling (BIM)-based Digital Twins remains scarce. This study develops a belief-based, probabilistic causal model of how AI-enabled BIM Digital Twin technologies may affect time-cost risks in Jordanian reinforced-concrete building projects. Using structured expert elicitation with 600 experienced practitioners (contractors, consultants, project managers, and academics), we capture expert judgements on causal links between four technology clusters-AI-based progress detection, contract-aware BIM assistants, predictive cost-schedule twins, and AI-assisted design/constructability-and key project mechanisms and outcomes. All quantitative results in this study come from these expert judgements; no project-level before-after performance data are used. Accordingly, results are reported as pooled expert beliefs under stated scenarios, not empirically validated predictions. Hierarchical Bayesian models pool elicited probabilities into a Bayesian Network (BN) representing collective expert beliefs, rather than observed project performance. Monte Carlo simulations, Global Sensitivity Analysis (GSA), and Expected Value of Perfect Information (EVPI) are then used to explore technology-adoption and policy scenarios and to rank influential levers. Experts believe that, under idealized, high-readiness conditions, AI-enabled BIM Digital Twins could sharply reduce the probabilities of schedule delays >20% and cost overruns >10%. These figures are belief-based, optimistic upper-bound expectations derived from expert judgement, not empirically measured or validated impacts. The Bayesian Network therefore serves as an uncertainty-aware decision-support tool for early policy and investment decisions in data-poor contexts. It highlights the roles of training, organizational readiness, and client demand alongside technology adoption.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- A BIM‐Based Probabilistic Approach for Risk Assessment in Construction ProjectsAdvances in Civil Engineering · 2026
- Optimizing construction risk management through BIM integration and strategic planningScientific Reports · 2026
- AI-Driven Optimization of Scheduling, Risk, and Sustainability in BIM-Enabled Construction Project ManagementArabian Journal for Science and Engineering · 2026
- Inferring latent system risk in interdependent construction systems using digital twinsConstruction Innovation · 2026
- An Uncertainty‐Aware Digital Twin Framework for Dynamic Cost Prediction and Decision Optimization in Transmission Engineering ProjectsEngineering Reports · 2026
- An uncertainty-aware 4D/5D digital-twin framework for cost estimation and probabilistic schedule control: field and benchmark validation from a Texas mid-rise projectDiscover Civil Engineering · 2026