Lessons learned from a staged approach to upstream fish passage at Site C, a new hydroelectric dam in northeastern British Columbia, Canada
Nicholas J. Burnett, Sarah Prior, Vincent Autier, Brent Mossop
BC Hydro (Canada)
Key points
From the paper's conclusion- Here we share key lessons learned from 15 years of planning, design, construction, and operation of the temporary and permanent facilities, which represented a unique effort involving a new and large hydroelectric development and construction sequencing approach.
Abstract
BC Hydro has completed construction of the Site C Clean Energy Project, which is the third hydroelectric dam on the Peace River in northeastern British Columbia, Canada. We implemented a staged approach to upstream fish passage at Site C, whereby a temporary upstream fish passage facility was operated during the river diversion phase of construction (2020 to 2024). Following the closure of the diversion tunnels and reservoir filling in the fall of 2024, we began operating the permanent upstream fish passage facility at the outlet of the generating station to provide for upstream fish passage during the operations phase of Site C. Here we share key lessons learned from 15 years of planning, design, construction, and operation of the temporary and permanent facilities, which represented a unique effort involving a new and large hydroelectric development and construction sequencing approach. Importantly, the surprises and mistakes we encountered – no matter the scale or implication – reinforced the unique opportunity to learn from the temporary facility and apply those learnings to the design, construction, and operation of the permanent facility. Our lessons learned span a wide range of topics and disciplines and should prove useful to practitioners, natural resource managers, biologists, and engineers involved in new or existing fish passage projects elsewhere.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Integrated numerical–physical modeling for optimizing riverbed dredging in Mixed Pumped-Storage Power Stations: a case study of Lianghekou projectScientific Reports · 2026
- Integrated Hydraulic and Biological Monitoring Reveals Stage-Specific Passage Performance in a Vertical-Slot Fishway in the Upper Yangtze RiverWater · 2026
- Responses of the whole life cycle of typical fish species in the upper Yangtze River to hydrological regime alterations and their ecological flow requirements.Environmental monitoring and assessment · 2026
- Mitigating Low Pressure in Draft Tubes of Pumped-Storage Units by Installing Tailwater Connection Pipes Under Successive Load Rejection Conditions: Mechanism and Effectiveness AnalysisWater · 2026
- Long-Term Geomorphological and Land Cover Changes Associated with a Run-of-River Hydropower Project in Ecuador’s Dulcepamba River BasinHydropower · 2026
- Hydraulic Control of Fish Distribution at Large River Confluences: Evidence for Cross‐Sectional Flow OrganizationWater Resources Research · 2026