Geomechanics and Tunnelling

TBM–rock mass interaction during tunnelling through a fault zone in the Brenner Base Tunnel: Insights from gripper extension measurements

Daniela Boldini, Matilde Bacci, Matteo Lanconelli

Key points

From the paper's conclusion
  • The results show that even minor reductions in rock mass quality can significantly deteriorate excavation conditions and lead to TBM blockage.

Abstract

This article presents a case study of double‐shield TBM excavation through a squeezing fault zone, highlighting a major challenge encountered during the construction of the Mules 2–3 section of the Brenner Base Tunnel. The fault, oriented orthogonally to the tunnel alignment, was identified during excavation of the exploratory tunnel and the eastbound main tunnel, where advance was achieved with relatively limited difficulties. In contrast, the westbound main tunnel machine became trapped while crossing the fault, requiring several countermeasures to resume excavation. Monitoring data and geological–geomechanical surveys were subsequently reinterpreted, and a back‐analysis of the rock mass mechanical properties was performed. Particular attention was given to records of gripper extension prior to each advance, which provided a direct estimate of incremental tunnel convergence at the gripper location and allow a reconstruction of the interaction between the rock mass and the shield during the blockage event. The results show that even minor reductions in rock mass quality can significantly deteriorate excavation conditions and lead to TBM blockage. An increased overcut of 50 mm would likely have prevented contact with the front shield.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers

TBM–rock mass interaction during tunnelling through a fault zone in the Brenner Base Tunnel: Insights from gripper extension measurements — Science Skim