BOLT: Multi-Bottleneck Bound-Guided Learning for Flexible Job-Shop Scheduling with Time Lags and Resource-Coupled Transport
Ziheng Zhang, Wei Zhang, Yunyi Zhao, Zuming Liu, Wei Zhou, Boon Ping Gan
Key points
From the paper's conclusion- BOLT decides in 2.3-5.9 ms per event on one processor core and re-plans a disruption in seconds.
Abstract
Flexible job-shop scheduling becomes resource-coupled when a scarce vehicle fleet moves jobs between stations, because the schedule sets the transport waits. BOLT (bound-oriented learning for transport-coupled scheduling) builds a lower bound from chain, machine-capacity, and fleet-capacity relaxations. The bound equals the makespan at termination, so its per-step changes form a reward that sums to a constant minus the makespan. Because it never exceeds the attainable makespan, each candidate's bound increase is a proven rise of the makespan floor, which the policy reads as a price. The root bound certifies a completed schedule's suboptimality gap without a solver. On industry-motivated 10-module prefabricated-construction instances, explicit transport coupling outperforms a transport-penalty policy in every tested cell where loaded moves occupy at least 66% of fleet time and in none at or below 56%. Across five zero-shot 50- and 80-module production batches, BOLT outperforms the best dispatching-rule pair on four and the penalty policy on the three with long moves. In the three-vehicle 80-module batch, its mean makespan is 13.0% below the best pair and 4.2% below an hour-budget constraint-programming solver whose proven gap averages 34%. BOLT decides in 2.3-5.9 ms per event on one processor core and re-plans a disruption in seconds.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- CoRS: Fast Neural Flexible Job-Shop Scheduling via Composite Interval State ReusearXiv · 2026
- Agent-written heuristics versus commercial solvers on unsolved job-shop benchmark instancesarXiv · 2026
- Dual Representation Enhanced Diffusion Policy for Flexible Job Shop SchedulingarXiv · 2026
- Job shop scheduling benchmark: environments and instances for learning and non-learning methodsAnnals of Mathematics and Artificial Intelligence · 2026
- Agentic AI-Assisted Modeling for Production Scheduling: Assessment in Constraint ProgrammingarXiv · 2026
- A neural-driven constructive heuristic for the flexible job shop scheduling problem: An efficient alternative to complex deep learning methodsComputers & Operations Research · 2026