Virtual Transmission Lines from Data Center Workload Migration: Coordinated Multi-Year Transmission Expansion Planning
Mengxin Zhu, Qian Kai, Yadong Liu, Yingjie Yan, Haoyu Zhao
Key points
From the paper's conclusion- The results show that coordinating VTL with physical transmission expansion reduces total system cost, unserved data-center load, and renewable-energy curtailment while alleviating transmission congestion.
Abstract
The rapid growth of electricity demand from AI data centers is creating a dual mismatch in power systems: a temporal mismatch between fast-rising demand and slow transmission expansion, and a spatial mismatch between concentrated data-center loads and geographically dispersed renewable resources. These mismatches can exacerbate transmission congestion, resulting in unserved data-center load and renewable-energy curtailment. This study models geographic workload migration as a virtual transmission line (VTL) that changes nodal data-center demand without transferring physical electricity. A mixed-integer linear programming model is then developed to co-optimize multi-year candidate-line construction and workload migration, subject to construction delays, renewable-energy curtailment, unserved data-center load, workload-balance requirements, communication-bandwidth constraints, and link-latency limits. The model is evaluated over an eight-year planning horizon on a modified IEEE 14-bus system. The results show that coordinating VTL with physical transmission expansion reduces total system cost, unserved data-center load, and renewable-energy curtailment while alleviating transmission congestion. VTL-aware planning also requires one fewer candidate line than build-only planning. However, VTL alone cannot meet system demand and does not eliminate the need for physical transmission reinforcement. Sensitivity analysis indicates that VTL provides the greatest value when transfer capacity is tight, construction costs are high, load growth is rapid, and data-center flexibility is greater. Additional validation on the IEEE 118-bus system over a five-year planning horizon shows that coordinated planning retains its cost and reliability benefits while reducing physical expansion requirements.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Quantifying the hosting capacity value of workload flexibility for AI data centers: A two-stage electricity-computation co-optimization frameworkarXiv · 2026
- N-1 Security constrained Hosting Capacity Assessment for Ultra Large-scale Data Center with Workload FlexibilityarXiv · 2026
- Design of Virtual Reserve Services Based on Spatially Transferable Loads in Data CentersEnergies · 2026
- Data center workload flexibility for power system demand response: Evidence from Alibaba tracesInternational Journal of Electrical Power & Energy Systems · 2026
- A Critical Review of Grid Integration Challenges and Flexibility Opportunities for Large-Scale Data CentersarXiv · 2026
- Flexible Training Workloads in Large-Scale AI Data Centers for Transient-Stability Support in Transmission-Constrained Power SystemsarXiv · 2026