Readiness for Change and Change Management: Stakeholder Evidence on Public–Private Partnership Success in Gulf Power and Water Projects
Khaled Aljaber, M. Sohail, Kirti Ruikar
Key points
From the paper's conclusion- We surveyed 300 stakeholders across 30 projects, randomly drawn from 62, in Kuwait, Saudi Arabia and the United Arab Emirates.
Abstract
Power and water public–private partnerships (PPPs) in the Gulf Cooperation Council (GCC) have delivered unevenly. Assessments centre on contracts, finance and risk. Prior work has examined readiness and change management largely outside PPPs. We surveyed 300 stakeholders across 30 projects, randomly drawn from 62, in Kuwait, Saudi Arabia and the United Arab Emirates. Responses within projects were selected purposively, so responses are nested within projects. Success was measured with a published and validated Project Success Index. A multiple regression on six factor groups explained 91.8% of variance (adjusted R2 = 0.916; F(6, 293) = 543.4; p < 0.001). All six were positive and significant. Organisational structures and processes (standardised β = 0.355) and individual and group dynamics (β = 0.320) had the largest estimated coefficients. Planning and external influences followed closely (β = 0.214 and 0.211). Managing resistance ranked lowest (β = 0.104). The design is cross-sectional and single-source, so the results show association, not causation. As a practical suggestion, sponsors and procurers may consider assessing readiness before financial close and managing change throughout the project lifecycle, although the timing of assessment was not tested.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Project Planning, Selection, and Implementation as Determinants of Project Success: A Systematic Review of Theory and PracticeInternational Journal For Multidisciplinary Research · 2026
- The impact of conflicts between government and private sector on the performance of PPP projectsInternational Journal of Managing Projects in Business · 2026
- Analyzing the critical factors of digital readiness for construction enterprisesEngineering Construction & Architectural Management · 2026
- Identifying Perceived Factors to Complete Progressive Design-Build (PDB) Project Successfully: An Exploratory Factor AnalysisBuildings · 2026
- Projects for change: reframing discontinuities within a public infrastructure agencyProject Leadership and Society · 2026
- Blockchain in Jordanian construction: an exploratory empirical study of stakeholder priorities and bootstrapped ROIFrontiers in Blockchain · 2026