A WBGT-Gated Digital Framework for Occupational Hazard Control in Gulf Mega-Project Construction: Design and Analysis with a Saudi Reference Case

Majed H. Moosa, Wael Alattyih, Osama M. Irfan, Ahmed A. Abdou El-Abbasy, Walid M. Shewakh

Key points

From the paper's conclusion
  • The practical implication for contractors and regulators is that heat control is a work-authorisation and shift-design problem before it is a monitoring problem.

Abstract

The construction of oil, gas and petrochemical mega-projects in the Gulf Cooperation Council (GCC) states combines high-hazard simultaneous operations with wet-bulb globe temperatures (WBGTs) that exceed occupational limits well before the statutory midday work ban begins. Existing digital tools advise, warn or monitor. None of them withhold a work permit, and that is the gap this paper addresses. Following a design-science approach, this paper specifies and analyses a digital occupational risk management (D-ORM) framework whose central and novel element is a permit engine gated on the measured or forecast WBGT rather than on clock time, with the gate failing safe when the measurement is unavailable. Saudi Arabia serves as the reference case; Qatar supplies the only existing GCC legal precedent for a measured WBGT trigger and is used here as a reference point, not as a proposed Saudi threshold. Five results follow, all of them analytical. A diurnal WBGT model calibrated to published Saudi field measurements places 68% of the daily heat load above 30 degrees Celsius before the Saudi ban starts, and a Monte Carlo perturbation of the model parameters keeps that share above half in 93% of draws. A heat factor applied to residual-risk scoring reorders the task hierarchy, and the ordering survives a plus-or-minus-one-point perturbation of the input scores in most draws. WBGT gating on a conventional day shift costs 54% of productive crew-hours, while a gated split shift recovers 58% of that loss; the same split shift also protects worker income, which falls to 0.46 of the baseline under a gated day shift but to only 0.73 under the split. ISO 1999 median threshold shift shows that an 85 dB(A) trade never reaches a 10 dB audiometric-priority threshold in a 40-year career, while a 95 dB(A) trade reaches it in 3.2 years, which places audiometric triage in the 90 to 95 dB(A) band. Detecting a lost-time injury frequency shift from 0.62 to 0.30 requires about 68 million work-hours per arm, which is beyond a single package-year and explains why such claims should not be asserted from scenario curves. All models are stated in closed form, the status of every number is declared, and no outcome is presented as observed. The practical implication for contractors and regulators is that heat control is a work-authorisation and shift-design problem before it is a monitoring problem.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers

A WBGT-Gated Digital Framework for Occupational Hazard Control in Gulf Mega-Project Construction: Design and Analysis with a Saudi Reference Case — Science Skim