System Value and Investor Incentives for Planned Nuclear Power in Uzbekistan: A Capacity-Expansion and Cournot Analysis
Dilnavoz Turaeva, Kang-wook Cho, Soo-jin Park
Key points
From the paper's conclusion- Of a gross system value of USD 884 million, before USD 1765 million of fixed charges, the owner’s operating profit was USD 496 million and the single buyer saved USD 460 million.
Abstract
Uzbekistan began building its first nuclear plant, at Farish, in 2026 while moving from a single-buyer model to a wholesale electricity market. Part of the plant’s value may accrue to the single buyer, which procures peaking capacity outside the market, and not to its owner. This study quantifies that division. A PLEXOS capacity-expansion model for 2026–2035 was linked to a two-stage Nash–Cournot game solved for every hour, and the plant’s welfare effect was split among owner, single buyer, other producers, and consumers under three procurement rules. The planned units displaced 1700 MW of open-cycle gas turbine capacity and raised system cost by USD 892 million at a 10% real cost of capital and USD 17 million at 4%. Of a gross system value of USD 884 million, before USD 1765 million of fixed charges, the owner’s operating profit was USD 496 million and the single buyer saved USD 460 million. When procurement was held fixed, the owner captured almost all of a smaller value. What the owner does not capture reflects unremunerated capacity value, which incumbent market power narrowed slightly. Within the model, concessional finance plus a capacity payment equal to the avoided procurement covered the owner’s 2026–2035 funding shortfall.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Repurposing gas power stations for modular nuclear and hydrogen systems: a techno-economic assessmentApplied Energy · 2026
- A type–capacity coupling planning method for wind–PV–storage micro-grid for maximizing the annual net revenueJournal of Engineering and Applied Science · 2026
- Beyond electricity generation: Nuclear power plants as circular chemical manufacturing hubs for plastic waste valorizationEnvironmental Progress & Sustainable Energy · 2026
- Kelayakan Finansial PLTS Atap On-Grid pada Gedung KomersialJTM JURNAL TEKNIK MESIN · 2026
- Sustainable District-Heating Transition in Poland: The Case of the City of UstkaSustainability · 2026
- Multiagent game-theoretic robust optimization for power system planning under source–load uncertaintyScientific Reports · 2025