Key points
From the paper's conclusion- The results demonstrate that using the TCI alone does not fully reflect the actual TC of the PUs, whereas the combined consideration of TC, CTR, and RL enables a more justified formation of M&R programs.
Abstract
The study develops and implements a methodology for prioritizing power units (PUs) of captive power plants (CPPs) to support the development of maintenance and repair (M&R) programs considering their actual technical condition (TC) and reliability indicators. The proposed approach is based on the joint assessment of the technical condition index (TCI), the consumed technical resource (CTR), and the risk level (RL) of the PUs. To describe the statistical patterns of failures, a two-parameter Weibull distribution is applied, while the temporal change in the TCI is approximated by a linear relationship that accounts for differences between actual and nominal operating conditions. The CTR is defined as an integral characteristic reflecting the deviation between the actual and nominal TCI degradation functions. The RL is evaluated as a function of the probability of failure and the consequences of PU failure. Based on these individual indicators, an integrated priority index is formed to provide an unambiguous ranking of PUs. The methodology was implemented using actual operational data from a fleet of PUs of an energy company. The results demonstrate that using the TCI alone does not fully reflect the actual TC of the PUs, whereas the combined consideration of TC, CTR, and RL enables a more justified formation of M&R programs. The practical significance of the study lies in the possibility of applying the developed methodology for reliability management of PUs at CPPs under resource constraints.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Reliability Analysis of Maintenance Data for Repairable Mechanical Devices in Nuclear Power PlantsScience and Technology of Nuclear Installations · 2026
- Advanced weibull reliability analysis for industrial pumping systems: An integrated framework for predictive maintenance optimizationResults in Engineering · 2026
- Optimal Hybrid Maintenance Policy for Protection Systems With Multiple Abnormal Operational BehaviorsQuality and Reliability Engineering International · 2026
- Scheduling maintenance activities subject to continuous stochastic job-dependent machine deteriorationEuropean Journal of Operational Research · 2026
- Reliability and Profit Analysis of a Cold Standby System With Priority and Two Types of RepairmenQuality and Reliability Engineering International · 2026
- Development of a Fuzzy Risk Model for Criticality Analysis of a 25 MW Dual-Fuel Power Plant in BangladeshSciEn Conference Series Engineering · 2026