A Hybrid Markov–Simulation Approach for the Design of Flexible Multi-Product Manufacturing Systems
Maxim Mikhailov, Igor Temkin, Sergey Deryabin, Alexander Muranov, Naur Ivanov
Key points
From the paper's conclusion- The chain reproduced the simulated processing and idle shares within 1.5% and, when excluding four of the seven machine numbers, reduced the simulation runs by 57% without changing the selection.
Abstract
High-mix manufacturing systems are vulnerable to stochastic equipment failures, changeovers and bottlenecks that deterministic capacity planning cannot adequately represent. This study develops a hybrid Markov discrete-event methodology for selecting bottleneck capacities in an unreliable serial–parallel multi-product foundry producing aircraft-engine components. A five-state discrete-time Markov chain of a bottleneck machine, derived from model inputs, estimates the stationary shares of processing, changeover, idle time, and two-phase repair and bounds the feasible configurations, whereas an AnyLogic model represents eleven operations, eight finite buffers, three product types, changeovers, and equipment failures. Replacing green-sand molding with cold-hardening mixtures and increasing the bottleneck from one to two parallel machines raised the bottleneck capacity from 15.1 to 26.6 workpieces per hour and reduced the shift-order makespan from 487 to 414 min, whereas a third machine added 5% capacity. Two machines maximized the constrained criterion of productive utilization, makespan, and resource intensity at every loading time, and the monthly plan was met for a cold-hardening yield of at least 0.63; a deterministic calculation overestimated the capacity by 7–49% and accepted a single machine, which, in simulation, completed only 20% of the shift orders within the shift. The chain reproduced the simulated processing and idle shares within 1.5% and, when excluding four of the seven machine numbers, reduced the simulation runs by 57% without changing the selection. Practitioners should validate the unit times, criterion weights, and yield against independent workshop data.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Mathematical Modeling of Operational Reliability of Mine Lifting Equipment Based on Censored DataMathematics · 2026
- Stacking-factor-integrated production planning for 3D-Stacked high-bandwidth memory manufacturing: an optimization approachFrontiers in Materials · 2026
- Markov-Based Stochastic Modelling of Operational Disturbances and System Availability in Robotic Masonry: Implications for Sustainable ConstructionSustainability · 2026
- Multistage Production–Quality–Maintenance Optimization Under Uncertain Quality-Deviation Propagation: A K-Adaptability ApproachProcesses · 2026
- Methodology for predicting the failure rate of mining machines with account of their multimode operationMining Industry Journal (Gornay Promishlennost) · 2026
- Optimization of the Dependability of a Hammer Mill Under Budgetary Constraints Using Evolutionary Algorithms, Stochastic Methods, and Statistical Performance AssessmentQuality and Reliability Engineering International · 2026