Economic Selection and Sequencing of Quality Improvement Projects Under Stochastic Process States: A Taguchi Expected Loss Approach

Ahmet Cüneyt Cedimoğlu, Efehan Koç, Muhammed Emir Kocabaş, Salih Tekin, Burak Birgören

Key points

From the paper's conclusion
  • A heterogeneous example further shows that evaluating projects using aggregate quality loss alone can lead to a less valuable portfolio when improvement mechanisms differ.

Abstract

Six Sigma project selection requires balancing expected quality improvements against implementation costs, durations, and limited resources. This study develops an economic evaluation approach based on Taguchi’s expected quality loss, modeling process mean shifts and dispersion changes as random process states and distinguishing their contributions to the expected loss. The avoided loss of each improvement project is derived according to its effect on these two components and incorporated into a deterministic mixed-integer programming model for budget- and horizon-constrained project selection and sequencing. For any selected portfolio, the optimal implementation order follows the weighted shortest processing time rule. In an illustrative scenario calibrated from published manufacturing cases, the project with the second-largest reduction in standard deviation (a scenario target) is excluded because of its cost and duration, although the budget is not binding. A heterogeneous example further shows that evaluating projects using aggregate quality loss alone can lead to a less valuable portfolio when improvement mechanisms differ. In a computational study of 3600 instances, six conventional prioritization rules fell more than 5% below the optimum in 30–86% of the 3369 instances with a profitable portfolio. The approach provides a reproducible economic criterion that complements multi-criteria project evaluation.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers

Economic Selection and Sequencing of Quality Improvement Projects Under Stochastic Process States: A Taguchi Expected Loss Approach — Science Skim