Time-Based Reconstruction, Uncertainty Assessment, and Prediction of Concurrent Water Supply Interruptions and Repair Work for Maintenance Engineering
Katarzyna Pietrucha-Urbanik, Barbara Tchórzewska-Cieślak, Mohamed Eid
Key points
From the paper's conclusion- For nominal 90% prediction intervals, the five-year-donor NB2 model covers 62.5% of monthly counts in the frozen assessment and 28.6% of annual counts across 14 January origins.
Abstract
Weekly counts and total durations can conceal overlapping water supply interruptions and repair work. Using 4885 entries from a municipal utility database in southeastern Poland (2004–2025), we assess aggregation loss (RQ1), sensitivity of reconstructed overlap (RQ2) and predictive reliability for maintenance planning (RQ3). Among 56 groups of weeks with identical counts and accumulated interruption and repair-work durations, 40 contain weeks differing in peak concurrency or threshold exposure. Associated repair work remains active at restoration in 96.86% of interruption episodes. The repair-work maximum of nine is reproduced by every fixed-count reference path. In separate sensitivity analyses, the maximum falls to seven after hypothetical grouping and to four after excluding 2007. The full-database maximum remains nine under endpoint changes of up to 30 min within recorded dates. OR (1,2) exposure spans 683.92–1572.25 h around 1061.42 h nominally. Five simulators show uneven calibration across January, April, July and October origins. For nominal 90% prediction intervals, the five-year-donor NB2 model covers 62.5% of monthly counts in the frozen assessment and 28.6% of annual counts across 14 January origins. Chronology supports audits of concentrated work and restoration timing; staffing decisions require verified job identifiers and resource data.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Fast Reassessment of Prolonged Electricity Shortages under Shared Fuel InterruptionsarXiv · 2026
- Correcting Left‐Truncation Bias in Weibull Reliability Analysis: Synthetic Data Validation for Electrical Utility AssetsQuality and Reliability Engineering International · 2026
- When Sensors Fail: Coverage Auditing with Incomplete Sensor RecordsarXiv · 2026
- Calendar‐Time and Gap‐Time Reliability Assessment of Repairable Tide‐Gauge Systems Using Crow–AMSAA and Hierarchical Weibull ModelsQuality and Reliability Engineering International · 2026
- A Hybrid LSTM–Weibull Framework for Estimating Phenolic Joint Seal Replacement Needs in the Generating Units of the Santo Antônio Hydropower PlantEnergies · 2026
- Probabilistic Repair Time Models of Buildings for Stochastic Simulations of Post‐Earthquake Community Recovery CurvesEarthquake Engineering & Structural Dynamics · 2026