From the paper's conclusion- These findings indicate that the combined control scheme can effectively reduce lateral abutment-pressure concentration and improve the stress environment of the gob-side entry while maintaining the load-bearing function of the support system.
Abstract
During fully mechanized top-coal caving in an extra-thick coal seam under a hard roof, suspended structures formed by multiple hard strata generate concentrated loads. Together with plastic failure of a narrow coal pillar, these loads exacerbate gob-side entry deformation. Key-strata identification, numerical simulation, and field monitoring were used to examine how coal-pillar width and roof-cutting height affect stress distribution in the 1521 return airway at Chaigou Coal Mine. The results are as follows: (1) A 10 m coal pillar places the entry in a relatively low-stress zone on the gob side of the lateral abutment-pressure concentration zone. (2) Roof cutting to heights of 30 and 100 m reduces the peak lateral abutment pressure by 9.6% and 35.2%, respectively. The corresponding reductions in the integral of the lateral abutment-pressure increment are 4.9% and 49.1%. Low-level roof cutting to 30 m primarily reduces local stress concentration and promotes stress redistribution deeper into the solid coal. At a roof-cutting height of 100 m, roof cutting encompasses intermediate- and high-level key strata and produces greater pressure relief. The additional stress reduction occurs mainly in the solid-coal rib, whereas the mean stress in the coal-pillar rib changes only slightly. (3) The field control scheme combined hydraulic fracturing of high- and low-level roof strata with high-pretension bolt-and-cable support and grouting reinforcement. Following its implementation, the maximum rib-to-rib and roof-to-floor convergence values during mining were 643 mm and 314 mm, respectively. No anchorage failure or abrupt load drop was observed in the cable bolts in either rib. These findings indicate that the combined control scheme can effectively reduce lateral abutment-pressure concentration and improve the stress environment of the gob-side entry while maintaining the load-bearing function of the support system.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Study on the stability of fully mechanized top-cutting pressure relief au-to-matic roadway formation under the effect of cutting depthEngineering Research Express · 2026
- A new path for pressure relief surrounding rock control of thick and hard roof combined blastingInternational Journal of Coal Science & Technology · 2026
- Mechanism and control of asymmetric deformation of surrounding rock in gob‐side roadway driving along narrow coal pillar in extra-thick coal seamResults in Engineering · 2025
- Determination of the Pressure-Relief Environment of Roadways Beneath the Goaf and Surrounding Rock Control for Gob-Side Entry Retaining by Roof CuttingApplied Sciences · 2026
- Mining-induced ground pressure hazards and roof strata movement in extra-thick coal seam extraction: A case study from Yanbei coal mine, China.Science progress · 2026
- Directional Presplitting Roof Cutting for Surface Subsidence Control in Extra-Thick Longwall Top-Coal Caving Under Thick Unconsolidated OverburdenProcesses · 2026