Can competition survive collaboration? Managing contractor involvement before award

Eric Scheepbouwer

Key points

From the paper's conclusion
  • The example compares four development strategies, identifies the probability thresholds at which the preferred response changes, and shows how supplier availability, takeover requirements and commercial evidence inform successive decisions.

Abstract

Before awarding a construction contract, clients may draw on contractor expertise to improve constructability, explore and develop alternative solutions, and obtain more reliable cost and programme estimates. Yet the same involvement can make it harder to change contractors or delivery approaches. Drawing on a bounded, purposive review of construction procurement research, economic theory and procurement guidance, this paper develops a framework for assessing such commitments. It distinguishes the availability of alternative contractors from the cost and time required to use them, and scrutiny of an incumbent’s developed price from comparison with alternative construction methods. Four testable propositions address early market mapping, supplier-specific dependencies, decisions to continue with an incumbent and the value of alternative-method comparisons. A six-step assessment procedure is applied at four decision gates in a hypothetical bridge project. The framework and propositions are developed conceptually, with their empirical assessment left for subsequent research. The example compares four development strategies, identifies the probability thresholds at which the preferred response changes, and shows how supplier availability, takeover requirements and commercial evidence inform successive decisions.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers