Study on problems associated with reactive maintenance of roads: A case of selected highways in Far-Western Nepal
Laxaman Datt Joshi, Khet Raj Dahal, Ravi Tripathi
Key points
From the paper's conclusion- Hence, this study was conducted with an aim to assess the major problems, causes and effects of reactive maintenance of roads and to draw effective mitigation measures for the Khodpe-Chainpur Highway (NH-64), Satbanjh-Gokuleshwor-Darchula section of Mahakali Highway (NH-66) and Anarkholi-Jhulaghat section of Mid-Hill Highway (NH-03).
Abstract
Road maintenance in the mid-hills and high hills of far-western Nepal is largely reactive, where interventions are made only after pavements, slopes and drainage structures have already failed. Such practice restores traffic temporarily but increases long-term cost and shortens the service life of roads, and very few studies have been carried out to find its root causes in the region. Hence, this study was conducted with an aim to assess the major problems, causes and effects of reactive maintenance of roads and to draw effective mitigation measures for the Khodpe-Chainpur Highway (NH-64), Satbanjh-Gokuleshwor-Darchula section of Mahakali Highway (NH-66) and Anarkholi-Jhulaghat section of Mid-Hill Highway (NH-03). Primary data were collected through field observation, in-depth interview, focus group discussion and questionnaire survey, whereas secondary data were collected from published journal articles, theses, government databases and annual reports. The data collected from 130 respondents were analyzed in Excel using the Relative Importance Index (RII) for Likert scale questions. The results showed that the major problem is escalating structural and geotechnical failures with the highest RII value of 0.80, followed by destruction of supporting works along the road and emergency cleaning of landslides and rockfalls (RII 0.78). Unmanaged vulnerable and unstable slopes, no maintenance of deformed retaining walls until they collapse, limited budget for periodic maintenance and the practice of awarding contracts to the lowest financial bid were identified as the main causes. Among the effects, cyclical budget exhaustion and repeated maintenance received the highest RII of 0.84, indicating that repeated emergency interventions impose a substantial financial burden on road authorities. The reactive maintenance cost of the studied road links ranged from NRs 41.65 thousand to NRs 231.05 thousand per km in F/Y 2026. To overcome these problems, shifting from emergency clearing to multi-year contracts in which contractors are paid for maintaining the target serviceability level throughout the year, routine hand clearing of small culverts and sealing of surface cracks, integrated slope and drainage management, and bioengineering for vulnerable slopes were identified as the most effective measures.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Problems, causes and impacts of landslides along the Beni–Jomsom–Korala Road in the Kaligandaki Corridor, NepalUniversal Technical Journal of Lumbini International Academy of Science and Technology · 2026
- Numerical Investigation of Deformation Response and Stress-Path Evolution in a Multilayer Road System Under Repeated Moving Vehicle LoadsApplied Sciences · 2026
- Identification of Landslide-Prone Areas and Mitigation Measures along the Proposed Chaumala–Garbha Road, Kailali, NepalUniversal Technical Journal of Lumbini International Academy of Science and Technology · 2026
- Road material stock and circularity potential in growing cities: the case of SingaporeEnvironmental Research: Infrastructure and Sustainability · 2026
- Overview of methods for strengthening collapsed sections of roads in the national road network – part 1 geological aspect of the problemIOP Conference Series: Earth and Environmental Science · 2026
- Eco-physical bioengineering for nature-based landslide mitigation in tropical rural landscapes: a conceptual review and secondary data synthesis from Kaliwiro-Wonosobo, IndonesiaIOP Conference Series: Earth and Environmental Science · 2026