IOP Conference Series: Earth and Environmental Science

Implementing Sustainable Construction using Modular Methods, Exposing the Impediments of Modular Manufacturing Companies in West Malaysia

Ahmad Bin Abd Jalil, Fadhilah Binti Md Fazil, Hazwani Shafei, Muhammad Fadhlullah Bin Abu Bakar

Key points

From the paper's conclusion
  • The findings proved that current modular manufacturers always facing insecure payment, lack of contractual rights, imprudent treatment compared to other subcontractors and frequently assume liabilities that are disproportionate to their actual risk exposure.

Abstract

Adopting sustainable construction is no longer optional and one of the approaches is via implementing modular methods. This construction technology is part of 2030 Sustainable Development Goals, fostered by United Nations in 2015 where modular methods are contained under SDG 11, creating sustainable cities and communities. The increasing population and economic activities coupled with eagerness to meet ESG and SDG targets, have led governments to enforce modular methods which aims to transform construction into sustainable, better quality, less manual labors, cost efficiency and speed. Modular methods require the whole system to be in smooth synchronization from designers, modular suppliers, builders, supply chain and service providers. Previous research discussed various problems on logistics, incentives, designs, products, process and quality controls, but lack on highlighting the current impediments faced by the modular manufacturing companies. They become the engine room of the project’s success as they constitute 70% of the building structure and are also responsible for the design, components’ manufacturing, transportation, installation and warranty. As current construction has changed due to environment regulations, stiff competition and fluctuation of prices, thus modular manufacturers also need to adapt with newer challenges. This research employs a mixed-method approach, comprising 129 questionnaire responses and 13 interviews with modular manufacturing companies, modular designers, installers, main contractors, consultants and clients. The study focuses on West Malaysia, where modular construction projects are most commonly implemented and where the majority of modular manufacturers operate for both domestic and export markets. The findings proved that current modular manufacturers always facing insecure payment, lack of contractual rights, imprudent treatment compared to other subcontractors and frequently assume liabilities that are disproportionate to their actual risk exposure. This research contributes on highlighting the verified current challenges that still obstructing the growth of modular manufacturers, making them demotivated and difficult to innovate, hard to survive, expand or attract investors for better inventions.

Read the paper