The Use of Fuzzy Logic and Least Cost Path Analysis for Mining Hauling Route Planning Based On UAV LiDAR Data
Gilang Diva Pradana
Key points
From the paper's conclusion- Against the existing route the optimised corridor reduced steep segment exposure by about 25 times, halved the mean slope, cut river crossings from three to one, and lowered earthwork by 32.8%, while being 2.2 times longer.
Abstract
Haul roads are heavily loaded corridors that serve the entire life of a mine, yet they are still frequently planned on the shortest distance principle, which drives routes across steep and morphologically complex terrain. The objective of this study is to develop and evaluate a reproducible corridor planning workflow from pit to port integrating UAV LiDAR terrain data, statistically parameterised fuzzy standardisation, and least cost path analysis, and to benchmark it against the route actually planned by the mine operator. Ground points classified by improved progressive TIN densification yielded a digital terrain model of LE90 = 0.2530 m, class 1 at 1:2,500 scale. Slope and absolute curvature were standardised with fuzzy Small and Linear membership functions whose midpoints and spreads were set from raster statistics and cross-checked against the design vehicle and the national haul road regulation, then combined by a fuzzy gamma overlay into a cost surface with hard constraints masked as impassable. Seven scenarios varying the slope, curvature, and gamma parameters all produced a single corridor of 26.3 to 30.0 km with mean slopes of 6.4 to 10.2% and only 0.87 to 3.50% of length on terrain steeper than 25%. The looser gamma scenario gave the lowest accumulated cost and the lowest maximum slope at a negligible length penalty. Against the existing route the optimised corridor reduced steep segment exposure by about 25 times, halved the mean slope, cut river crossings from three to one, and lowered earthwork by 32.8%, while being 2.2 times longer. A first-order assessment translates this into a haulage premium near USD 2.1 per tonne against an earthwork saving near USD 18 million, so the preferred alignment depends on production rate, mine life, and the feasibility of deep cuts. The workflow makes that trade-off explicit and quantifiable at the pre-design stage.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Estimation of Cut and Fill and Removed Tree Volume for Forest Road Design Using Fused Aerial and Terrestrial Laser Scans: A Case Study from Oregon, USARemote Sensing · 2026
- UAV-LiDAR Surveying of Forest Engineering Projects: A High-Resolution Workflow for Mapping Forest Roads and Stream-Crossing StructuresE3S Web of Conferences · 2026
- Trail erosion assessment and monitoring in natural areas: a comparison of traditional and high-resolution topographic surveying methodsEnvironmental Monitoring and Assessment · 2026
- Environmental–Economic Trade-Offs in Multimodal Construction Transport for Mountainous Power Transmission Lines: A RUSLE–Pareto FrameworkApplied Sciences · 2026
- UAV Inspection Modeling and Hierarchical Optimization Scheduling for Complex Open-Pit Mining AreasSymmetry · 2026
- Fuzzy Terrain Traversability Assessment and Adaptive Artificial Potential Field for Unmanned Ground Vehicle Control Based on Light Detection and RangingMathematics · 2026