Crane barge selection for offshore platform decommissioning: a multi-criteria decision using AHP and PROMETHEE
Rizal Hidayat Fadillah, Ketut Buda Artana
Key points
From the paper's conclusion- The analysis uses actual decommissioning data from a Production Sharing Contract (PSC) facility in the West Madura Offshore area and evaluates four crane barge alternatives under two execution scenarios: full removal to a junkyard and reefing in situ.
Abstract
Abandonment and Site Restoration (ASR) represents the final stage of the oil and gas production lifecycle and is regulated under PTK 040 SKK Migas Rev. 2 (2023). With a growing number of aging offshore platforms in Indonesia, the demand for decommissioning activities is increasing significantly. These operations involve complex processes, including topside lifting, jacket removal, controlled lowering, and transportation to shore, all of which require suitable crane barge support. This study determines the most suitable crane barge for offshore decommissioning by integrating a Work Breakdown Structure (WBS), the Analytic Hierarchy Process (AHP), and PROMETHEE. The analysis uses actual decommissioning data from a Production Sharing Contract (PSC) facility in the West Madura Offshore area and evaluates four crane barge alternatives under two execution scenarios: full removal to a junkyard and reefing in situ. The AHP results show that safety is the dominant criterion group. The aggregated weight of the safety-related sub-criteria is 0.471, followed by technical suitability at 0.301, implementability at 0.122, and cost at 0.106. The PROMETHEE II results indicate that EN3000 is the preferred alternative for the full removal scenario with a net flow of 0.235, closely followed by TM 1201 with 0.216. For Scenario B, TM 1201 becomes the most preferred alternative with a net flow of 0.574 due to its DP2/station-keeping capability, controlled lowering suitability, and lower risk to existing subsea facilities. The sensitivity analysis confirms that the Scenario B ranking is more robust, while the full removal result remains sensitive to technical and safety weight variations.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Decision-Making Model for Revitalization of Non-Performance Diving Spread Assets Based on Risk, Operational Availability, and Cost at PT Pertamina Marine EngineeringIOP Conference Series: Earth and Environmental Science · 2026
- Optimization of MR Tanker Fleet Renewal Strategy Based on Qualitative Condition Assessment, Monte Carlo Simulation, and AHP for IMO Decarbonization Compliance: A Case Study of PT Pertamina International ShippingIOP Conference Series: Earth and Environmental Science · 2026
- Comments: Offshore Platform Recycling: Bold Idea, Few ExamplesJournal of Petroleum Technology · 2026
- An integrated AHP–PROMETHEE II–ILP framework for shipyard capability assessment and docking repair allocation of a tanker and gas carrier fleetIOP Conference Series: Earth and Environmental Science · 2026
- XAI–MCDA-HoDEM: An Explainable Multi-Criteria Decision Framework for Maritime and Port DecarbonizationGases · 2026
- Cost-driven design and optimization of steel support structures for offshore energy platforms: a review of CAPEX cost modelsFrontiers in Energy Research · 2026