Real-Time Construction Progress Reporting Leveraging Building Information Modeling and Microsoft Power BI for the High-Rise Construction Project

Somjintana Kanangkaew, Natee Suriyanon, Damrongsak Rinchumphu, Kengkard Sriparn, Noppadon Jokkaw, Dikai Pang, Pongammard Kanangkaew

Key points

From the paper's conclusion
  • The results showed that real-time construction progress reporting leveraging Building Information Modeling and Microsoft Power BI, presented via dashboards with 3D visualizations, significantly improved the understanding of construction progress, enhancing accuracy, clarity, and project management efficiency.

Abstract

Currently, construction projects in Thailand are experiencing rapid growth, particularly for large-scale buildings with complex structures, high budgets, and tight construction timelines. Construction progress reporting is a crucial step in project management to inform stakeholders of the project status, which helps ensure the smooth and efficient execution of construction work according to plan. However, construction progress reporting is typically presented in 2D formats, such as Gantt charts, tabular reports, and pie charts, which can be complex and challenging to understand. These methods require significant time to gather data and are prone to errors. This study aimed to propose real-time construction progress reporting leveraging Building Information Modeling and Microsoft Power BI to present construction progress for construction projects, particularly in the structural phase. The results showed that real-time construction progress reporting leveraging Building Information Modeling and Microsoft Power BI, presented via dashboards with 3D visualizations, significantly improved the understanding of construction progress, enhancing accuracy, clarity, and project management efficiency. In addition, the time required to implement the proposed system to create the real-time construction progress reporting of the case study is 15 hours, a significantly faster approach than the conventional method. Additionally, the investment and operation costs of the implementing proposed system were 153,177.28 and 20,000 Baht per month, respectively.

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers