Real-Time Construction Progress Reporting Leveraging Building Information Modeling and Microsoft Power BI for the High-Rise Construction Project
Somjintana Kanangkaew, Natee Suriyanon, Damrongsak Rinchumphu, Kengkard Sriparn, Noppadon Jokkaw, Dikai Pang, Pongammard Kanangkaew
Key points
From the paper's conclusion- The results showed that real-time construction progress reporting leveraging Building Information Modeling and Microsoft Power BI, presented via dashboards with 3D visualizations, significantly improved the understanding of construction progress, enhancing accuracy, clarity, and project management efficiency.
Abstract
Currently, construction projects in Thailand are experiencing rapid growth, particularly for large-scale buildings with complex structures, high budgets, and tight construction timelines. Construction progress reporting is a crucial step in project management to inform stakeholders of the project status, which helps ensure the smooth and efficient execution of construction work according to plan. However, construction progress reporting is typically presented in 2D formats, such as Gantt charts, tabular reports, and pie charts, which can be complex and challenging to understand. These methods require significant time to gather data and are prone to errors. This study aimed to propose real-time construction progress reporting leveraging Building Information Modeling and Microsoft Power BI to present construction progress for construction projects, particularly in the structural phase. The results showed that real-time construction progress reporting leveraging Building Information Modeling and Microsoft Power BI, presented via dashboards with 3D visualizations, significantly improved the understanding of construction progress, enhancing accuracy, clarity, and project management efficiency. In addition, the time required to implement the proposed system to create the real-time construction progress reporting of the case study is 15 hours, a significantly faster approach than the conventional method. Additionally, the investment and operation costs of the implementing proposed system were 153,177.28 and 20,000 Baht per month, respectively.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- IMPLEMENTASI PENGGAMBARAN, PENJADWALAN, DAN ESTIMASI BIAYA DENGAN METODE BIMCRANE Civil Engineering Research Journal · 2026
- Lean construction and BIM in construction projects: A literature review (2015–2025)Organization, Technology and Management in Construction: an International Journal · 2026
- Utilization of Building Information Modeling (BIM) for mitigating construction risksJournal of Engineering and Applied Science · 2026
- A comprehensive review on building information modelling (BIM), its implementations and applicationsDiscover Civil Engineering · 2025
- Indoor scan-to-BIM workflows: Progress, challenges, and future directions (2014–2024)Automation in Construction · 2025
- Digital transformation in construction: Assessing BIM’s contribution to sustainable built environmentsResults in Engineering · 2026