Integrating Data-centre Load Growth in Energy System Optimisation: Effects on the Generation Mix and Energy Networks
Matteo Catania, Fabrizio Fattori, Paolo Colbertaldo
Key points
From the paper's conclusion- Overall, the findings suggest that preparing for data-centre growth requires prioritising grid planning and system integration.
Abstract
The rapid growth of digital services is creating a new and uncertain electricity load from data centres. In Italy, grid connection requests are approaching 100 GW e , with strong regional concentration and limited information on actual deployment and timing. This may become a demand shock, thus raising a system-level question: can a large, spatially clustered increase in the electric load alter the cost-optimal evolution of the energy system towards decarbonisation? We address this question with FENICE (Future Energy traNsition multI-seCtor modEl), a long-term energy system model that co-optimises investment and operation across the time horizon of the transition, to meet demand at minimum total system cost under decarbonisation constraints. Data centres are represented as an exogenous electricity demand term, under alternative assumptions on magnitude, timing, and regional distribution, consistently with the observed connection requests. The model endogenously adapts generation and flexibility options, such as renewables, dispatchable capacity, storage, and carbon capture, while accounting for interactions with electricity and gas/hydrogen networks. Results indicate that additional data-centre electricity demand mainly amplifies investment requirements already implied by net-zero pathways, without triggering a qualitatively different transition. Outcomes are particularly sensitive to network constraints: the expansion of electricity grid and hydrogen infrastructure can accommodate new concentrated demand, reduce the need for local firm generation, and limit system costs. Across the investigated cases, substantial renewable build-out remains central to the least-cost mix, while low-carbon firm resources and flexibility options play complementary roles. Overall, the findings suggest that preparing for data-centre growth requires prioritising grid planning and system integration. The timing and location of new loads affect optimal investments, and the system response is shaped by energy transport across regions.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Moving bits instead of watts: Accelerating global AI data-centre deployment at the energy-digital-water-land nexusarXiv · 2026
- Evaluating the Dispatchable Capacity of Cross-Regional Data Center Clusters Toward Power System OperationIEEE Transactions on Smart Grid · 2025
- Comparative analysis of multi-scale optimization and simulation approaches for district heating decarbonizationJournal of Physics: Conference Series · 2026
- Spatial governance of China’s data-center expansion as a climate-action lever under resource and digital lock-inFrontiers in Environmental Science · 2026
- Integrating Data Center Flexibility into Power System Operations: A Framework for Temporal RedispatcharXiv · 2026
- Governing the Unmeasured Load: Hyperscale Data Centres, Systemic Risk and the Assessment–Management Gap in EU LawEuropean Journal of Risk Regulation · 2026