Hybrid Lean flow optimization using one-piece flow and controlled decoupling in a resin filling production line
Cakra A. Pratama, Taufik R. Sahroni
Key points
From the paper's conclusion- The results show how continuous-flow stages and technically constrained curing stages can be combined within one controlled production flow.
Abstract
Manufacturing improvement often targets shorter lead time, lower work-in-process (WIP), and better use of existing resources. In resin filling production, full one-piece flow is difficult because filling and curing require several hours of technical waiting. This research evaluates an industrial improvement project that combined one-piece transfer in Assembly and Main Assembly with tray-based flow, controlled decoupling, First-In, First-Out (FIFO) release, and an explicit WIP limit at filling and curing. Product-family focusing, two-bin Kanban, workload redistribution, and layout improvement supported the redesigned flow. Direct manpower decreased from 18 to 16 operators per shift, documented work content was reduced by 40 s/unit, calculated maximum line capacity increased from approximately 1,225 to 1,693 pieces/day, aggregate Manufacturing Order (MO) efficiency increased from 101.49% to 114.56%, and mean MO lead time decreased from 3.62 to 2.61 working days. Daily efficiency differed significantly between the pre- and post-implementation periods (MannWhitney, p < 0.001; Cliffs Delta δ = 0.621), while Hedges' g = 1.214 indicated a large standardized mean difference. The results show how continuous-flow stages and technically constrained curing stages can be combined within one controlled production flow.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Investigation into the Impact of Leagile Manufacturing Implementation in a Modern Mechanical WorkshopEng · 2026
- Leveraging Six Sigma DMAIC for Lean Implementation in Mechanical WorkshopsApplied Sciences · 2025
- From balanced scorecard to continuous flow metrics: Evolving performance measurement for Kaizen-driven organizationsBusiness Performance Review · 2026
- Implementing Lean Construction Principles in Civil Infrastructure Projects: An Analytical Framework for Productivity Enhancement and Waste EliminationBuildings · 2026
- Maximizing cleaning efficiency and minimizing rework in a recycling facility using the DMAIC approachProduction Engineering Archives · 2025
- Exploring Lean Manufacturing Integration and Performance Evaluation for Process Optimization in the Food Processing IndustryProduction Engineering Archives · 2026