Assessing the impact of construction material waste drivers on project cost overrun across material processing stages: a structural equation modeling approach.
Lobna Kamal, Mohamed S Yamany, Hossam E Hosny, Student
Department of Construction Engineering, Faculty of Engineering, Zagazig University, Zagazig, 44519, Egypt. · Department of Construction Engineering, Faculty of Engineering, Zagazig University, Zagazig, 44519, Egypt. mohamedyamany9@gmail.com.
Key points
From the paper's conclusion- The results demonstrate that factors related to material handling, storage, and transportation exhibit the highest correlation and impact on project cost overruns, as reflected by an R2 value of 0.441 and a p-value below 0.05.
Abstract
A considerable quantity of materials supplied to construction sites becomes waste, hence escalating project costs. Nevertheless, research lacks a thorough assessment of the intricate, indirect, and non-linear correlation between material waste drivers at different processing stages and project cost overruns. This research study investigates this correlation using an advanced multivariate statistical technique known as structural equation modeling (SEM). Data were collected through a questionnaire survey to evaluate the construction material waste factors (CMWFs) and their association with cost overruns in construction projects in Egypt. An exploratory factor analysis was conducted to categorize CMWFs into material processing phases: (1) design and documentation, (2) material procurement, (3) material handling, storage, and transportation, and (4) on-site management. An SEM model was developed to uncover the impact of latent material processing phases on project cost overruns. The model's consistency, reliability, and accuracy were verified employing various performance metrics, including Cronbach's Alpha, composite reliability, and root mean squared error. The results demonstrate that factors related to material handling, storage, and transportation exhibit the highest correlation and impact on project cost overruns, as reflected by an R2 value of 0.441 and a p-value below 0.05. This research helps decision-makers prioritize mitigation strategies for material waste and cost overruns, hence enhancing construction project performance.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Advanced digital solutions for construction waste management: A 4D BIM integrated scenario analysisGreen Technologies and Sustainability · 2025
- Predicting Waste Generation During the Construction of a Secondary School: A Case StudyBuildings · 2026
- Assessing construction material waste in Egypt through stakeholder estimationDiscover Sustainability · 2026
- Performance Evaluation in Construction Material Supply Chains: A Systematic Literature ReviewIOP Conference Series: Earth and Environmental Science · 2026
- Circular economy transition barriers in the construction and demolition sectorPLoS ONE · 2025
- Improving Waste Management at Construction Sites—Evidence from a Comparative Study in Poland and SlovakiaBuildings · 2026