Automated design of heuristics for resource-constrained project scheduling problem via regression algorithms
Jun Luo, Mario Vanhoucke, José P. Coelho, Jie Song
McGill University · Ghent University
Key points
From the paper's conclusion- To address this gap, this research explores the potential of supervised learning algorithms, specifically regression-based methods, for the automated design of new priority rule heuristics for RCPSP.
Abstract
Abstract The resource-constrained project scheduling problem (RCPSP) is a complex optimization problem aiming to construct feasible schedules that minimize the project makespan while satisfying the precedence and renewable resource constraints. Priority rule heuristics are prevalent approaches for solving the RCPSP, particularly in practical applications. However, these rules are problem-specific, and no rule can consistently outperform others across different projects. Designing priority rules through manual methods requires substantial expertise, time, and computational effort. This has led researchers to propose automated techniques for this purpose. Most existing research in this area focuses on unsupervised learning techniques like genetic programming hyper-heuristics (GPHH), while the investigation of supervised learning algorithms remains limited. To address this gap, this research explores the potential of supervised learning algorithms, specifically regression-based methods, for the automated design of new priority rule heuristics for RCPSP. Nine widely used regression algorithms were evaluated, and the top-performing three were further enhanced using ensemble techniques to augment their effectiveness. Computational experiments show that regression-based heuristics can outperform traditional priority rules across all primary test datasets and, in some cases, even surpass priority rules designed through GPHH. To further validate the reliability of our results, we also tested the regression-based heuristics on various supplementary datasets, including project instances with more than 1,000 activities and empirical projects. Their performance highlights the robust generalization of regression-based heuristics.
Read the paper
Discussion
Science Skim's AI key points, plus readers' public thoughts
Readers' thoughts
No reader thoughts yet.
Related papers
- Automated Priority Rule Design for the Resource-Constrained Project Scheduling Problem: A Large Language Model-Guided Population-Based SearcharXiv · 2026
- Review of recent advances on the resource-constrained project scheduling problemInternational Journal of Production Research · 2026
- A Surrogate-Assisted Evolutionary Framework with Verified Policy Feedback for Resource-Constrained Multi-Project SchedulingJournal of Computational Design and Engineering · 2026
- An expert-informed multi-scale synthetic benchmark dataset for calendar-aware resource-constrained project scheduling (CA-RCPSP).Data in brief · 2026
- Two Communities, One Problem: Branch-and-Bound vs. A* for Resource-Constrained Project SchedulingarXiv · 2026
- Enhancing Decision Intelligence Using Hybrid Machine Learning Framework with Linear Programming for Enterprise Project Selection and Portfolio OptimizationAI · 2026