Geomechanics and Tunnelling

2 nd S‐Bahn Main Line Munich – Marienhof Station: Prediction and monitoring of deformations for the deep excavation

Werner Felber, Jonas Wiser

Key points

From the paper's conclusion
  • During construction, the deformations of the excavation pit structure, the existing structures and the surrounding soil were monitored by numerous monitoring systems.

Abstract

The excavation for the more than 40 meters deep Marienhof station requires the resolution of complex geotechnical challenges due to the intricate design of the deep excavation and the presence of nearby existing structures. Extensive 3D finite element (FE) analyses were performed to predict the deformations of the excavation pit and the existing structures. During construction, the deformations of the excavation pit structure, the existing structures and the surrounding soil were monitored by numerous monitoring systems. The measured deformations were compared with the deformation predictions throughout the construction process (target‐actual comparison).

Read the paper

Discussion

Science Skim's AI key points, plus readers' public thoughts

Readers' thoughts

No reader thoughts yet.

Related papers

2 nd S‐Bahn Main Line Munich – Marienhof Station: Prediction and monitoring of deformations for the deep excavation — Science Skim